System Design and Integration, lesson 12 of 12

A complete design, start to finish

This last lesson takes one building through every step of the course. You will watch a customer's worry become requirements, the requirements become four systems, and the systems become the drawings, counts, hours and specification that someone can build from. Nothing here is new. The point is to see it all joined up.

About 16 minutes. Read the rest of the course first.

One building, four systems

A printing company, seen as a slice through the building. Look at one system at a time, then all of them together.

Lobby Production Dock Offices Server room Stairs street yard cabinet

R card reader at a controlled doorC cameraM motion detectorD door contactK keypadS sirenI intercom station

devices on the plan
cable runs to the cabinet
switch ports used

    The everyday picture

    A recipe book teaches you to chop, to make a sauce, to roast and to bake, one chapter at a time. Cooking a dinner for guests is a different skill. Everything has to be planned backward from the moment people sit down, and each dish has to suit the others.

    You have learned the chapters. This lesson is the dinner. Watch how each step uses the output of the one before.

    The need and the survey

    The customer is a printing company with 45 staff in a two-story building. Production and a loading dock are on the ground floor. Offices and a small server room are upstairs. The owner calls after two things happen in one month: pallets of paper go missing from the dock, and a former employee is found in the offices one evening, having walked in through the dock.

    As From need to design taught, the owner's words are a starting point, not a design. "We need cameras" becomes, after an hour of questions, three real needs: know who comes in, stop people wandering from the dock into the rest of the building, and know about anyone inside at night.

    The site survey fills in what the plan cannot show. The lobby and offices have lift-out ceiling tiles. Production has an open roof 22 feet up. The server room has a spare outlet and room on the wall. The front entrance is a pair of glass doors with no latch. The dock has a roll-up door and a steel staff door beside it. Drivers currently bang on that door until someone hears.

    Requirements

    The needs are written as requirements and sorted, as in Requirements and priorities. Each one is something that can later be tested.

    No.RequirementPriorityDelivered by
    1Only people with a valid card can pass from the lobby or the dock into production, or reach the upper floorMustAccess control, doors 2, 3, 4 and 6
    2Only named IT staff can enter the server room, and every entry is recordedMustAccess control, door 5
    3A leaver's card stops working at every door within minutesMustAccess control software
    4Anyone inside when the building is closed raises an alarm that is monitoredMustIntrusion system
    5Recorded video shows a face at each entrance and activity at the dock, kept 30 daysMustVideo
    6Staff can see and speak to a driver at the dock, and release the door, from receptionShouldIntercom, linked to access control
    7A forced door brings up the nearest cameraShouldIntegration
    8Cameras cover the whole parking lotCouldLeft for a later phase

    Architecture and integration

    Choosing an architecture asked where each system's brain should live. For a single building with its own server room and no IT department to speak of, the answers are modest.

    • Access control: two four-door controllers in the server room cabinet, managed by software on a small server on site. The controllers hold the card list, so doors keep working if the server stops.
    • Video: eight network cameras recorded on one recorder on site, sized for 30 days.
    • Intrusion: one panel with eight zones in use, sending signals to a monitoring station.
    • Intercom: two door stations and one desk station at reception, on the network.
    • Network: one switch with power for cameras and intercom, kept apart from the office computers.

    Integration is where the systems begin to act as one. Each link below exists because a requirement asks for it.

    When this happensThis systemTells this system toRequirement
    A door is forced or held openAccess controlVideo: mark the recording and show the nearest camera7
    Reception presses the release button on the desk stationIntercomAccess control: unlock door 3 for a few seconds and log it6
    The first valid card of the day is presented at the front entranceAccess controlIntrusion: disarm, if that person is allowed to4
    The intrusion system raises an alarmIntrusionVideo: mark the recording on cameras in that area4, 5
    The fire alarm soundsFire alarmAccess control: release the front entrance magnetic lockLife safety

    Check yourself

    The owner asked for "cameras". Why does the design include card readers and an alarm panel as well?

    Drawings and counts

    The design is drawn as floor plans, a riser diagram and schedules, as in Drawings: plans, risers and schedules. The door schedule is the heart of it.

    DoorLockWithout powerExit byNotes
    1 Front entrance, glass pairMagnetic locksUnlocksSensor and push buttonReleases on fire alarm. Agree with the authority.
    2 Lobby to productionElectric strikeStays lockedLever
    3 Dock staff doorElectric strikeStays lockedPush barIntercom release
    4 Stair door, upper floorFire-rated electrified lockAs the authority requiresLeverFire door on an exit route
    5 Server roomElectric strikeStays lockedLeverAlso has an alarm contact
    6 Dock to productionElectric strikeStays lockedLever

    Then comes the takeoff from Device and cable counts. The panel at the top shows the totals: 27 devices and 27 cable runs. Sixteen switch ports are used: eight cameras, three intercom stations, two controllers, the recorder, the intrusion panel and the link to the office network.

    Cable is totaled by type. The eleven network runs for cameras and intercom average 120 feet of route. Each adds 10 feet of rise and drop and 13 feet of slack, making 143 feet. Eleven runs come to 1,573 feet, and 10 percent waste brings the order to about 1,730 feet, so two boxes. No route is longer than 230 feet, so every run is inside the limit for copper.

    Hours

    Estimating labor and cost turns the counts into time. The labor units are the examples from that lesson, with three more for the new device types.

    TaskUnit, hoursCountHours
    Pull and support a cable run1.02727.0
    Terminate and test a run0.52713.5
    Mount and aim a camera1.088.0
    Fit out a door4.5627.0
    Mount a motion detector0.7543.0
    Fit a door contact0.542.0
    Mount keypad and siren1.022.0
    Mount an intercom station1.534.5
    Build and wire the cabinet8.018.0
    Program all four systems and the links between them12.0112.0
    Test, train and hand over10.0110.0
    Field hours117.0

    Management at 15 percent adds 17.6 hours, for about 135. A two-person crew works 16 hours a day, so the job needs 8.4 days. Book nine.

    The survey changes this figure. Three cameras and two detectors hang from the 22-foot roof in production and the dock, so those tasks and their cable pulls carry a height factor, and a lift goes on the list of rentals. The electrician, the fire alarm company and the door hardware installer for door 4 are subcontractors with written quotes. Materials are priced by suppliers on the day.

    Specification, growth and review

    Specification. Each must-have becomes a clause that can be tested. Requirement 5 becomes: "Cameras at doors 1 and 3 shall show a face in the doorway at 40 pixels per foot or more by day and by night. The system shall retain recordings from all cameras for at least 30 days." The acceptance test lists every door in every state and every link in the integration table.

    Growth. Sixteen ports with a quarter spare is 20, so the switch has 24 ports. Six doors on two four-door controllers leave two spare. The intrusion panel is a model that can take more zones. A spare conduit runs from the server room to the roof space over production, ready for the parking lot cameras in requirement 8.

    Failure. The riser diagram is checked box by box. The switch, recorder and server sit on a UPS, so a short power cut does not erase the video. Settings for every device are saved, and the customer accepts in writing that a failed recorder means no recording until it is replaced the next working day.

    Review. A second designer, the lead installer and the owner go through the set. Three findings matter. The installer points out that door 4 needs a power transfer hinge and a fire-rated frame preparation, which is added to the door hardware quote. The second designer notices the dock camera was drawn facing the open roll-up door, where daylight would turn people into silhouettes, and it is moved to look along the dock. And the walk-through of an ordinary evening reveals that the cleaners arrive after the alarm is set. Their cards are given the right to disarm.

    Follow the thread

    Pick a step to see what it produced for this building, and what it handed to the next step.

    Eleven steps, one design

    Handed on

    Three examples

    Simple: one requirement, followed through

    Requirement 2 says only IT staff may enter the server room. It becomes door 5 on the plan, a row in the door schedule, a reader, a strike and a contact in the bill of materials, 4.5 hours in the estimate, an access level in the software, a clause in the specification and a line in the acceptance test. Seven documents, one thread. If any link is missing, the requirement is not really in the design.

    Medium: the door that belonged to two systems

    The dock staff door has a reader, a strike, an intercom station outside, a camera above and an alarm contact. Four systems meet at one steel frame. On the first draft, the intercom's own relay was drawn wired straight to the strike. It would have opened the door without the access system knowing, so the door would then report as forced, and the event log would show an alarm every time a driver was let in.

    The fix was to have the intercom ask the access controller to unlock the door. The controller releases the strike, logs who was at the desk, and does not raise a forced-door alarm. Devices that share a door must agree on which one is in charge of it.

    Advanced: the budget arrives

    The price is higher than the owner hoped. A poor response is to shave every system a little. The design team goes back to the priorities. Every must stays. The could was already left out. Of the shoulds, the owner keeps the dock intercom, because drivers banging on the door interrupt production daily, and gives up the automatic camera call-up on a forced door for now.

    The team also changes the plan of work: the customer's own electrician provides the outlets, and installation happens in normal hours with production running. The system that results is smaller than the first proposal and still meets every must. The cable and spare capacity for what was deferred are left in place, so adding it later is cheap.

    From the field

    • Keep one numbering scheme for doors, cameras and zones across every document and every system's software.
    • Hold one meeting with every trade that touches a door: hardware, electrician, fire alarm and you.
    • Keep the requirements list open on the desk through the whole job. It settles most arguments.
    • Hand over a single folder: record drawings, schedules, settings, test results, passwords handed to a named person, and who to call.
    • Go back after a month. Ask what annoys people. Small adjustments then prevent propped doors and ignored alarms later.

    Common mistakes

    • Designing each system separately and meeting the others for the first time on site.
    • Losing the thread: devices with no requirement, or requirements with no test.
    • Cutting cost evenly across everything instead of by priority.
    • Treating the estimate, the specification and the review as paperwork to do after the "real" design.
    • Handing over equipment without handing over the knowledge to run it.

    Summary

    • A design is a chain: need, survey, requirements, architecture, integration, drawings, counts, hours, specification, growth and failure, review.
    • Each step uses what the one before produced.
    • Every device traces back to a requirement and forward to a test.
    • Where systems share a door or an event, decide which one is in charge.
    • When money is short, cut by priority and leave room to add the rest.

    Exercises

    Answer each one yourself first, then open the answer. The panel at the top will help.

    Exercise 1. Using the panel at the top, how many switch ports does the video system use by itself, and why is it one more than the number of cameras?

    Show answer
    Nine. Eight cameras and the recorder each need a port.

    Exercise 2. The owner later adds two cameras for the parking lot. Do they fit the switch, the estimate method and the cable order?

    Show answer
    The switch has 24 ports with 16 in use, so 18 fit easily. Check the power budget as well. Labor adds two pulls, two terminations and two cameras: 2 × (1.0 + 0.5 + 1.0) = 5 field hours, more if a lift is needed outside. Cable adds two runs, measured along the route through the spare conduit, and checked against the limit for copper.

    Exercise 3. Field hours are 117. If the three cameras and two detectors at height, with their five cable pulls, carry a factor of 1.3, how many hours are added?

    Show answer
    The affected hours are 3 cameras × 1.0, 2 detectors × 0.75 and 5 pulls × 1.0, which is 3 + 1.5 + 5 = 9.5 hours. A factor of 1.3 adds 30 percent of that: 2.85 hours, making 119.85 field hours.

    Exercise 4 (think, don't memorize). Six months after handover the owner says, "It works, but people prop the lobby door open all day." Which steps of the design would you revisit, and what might change?

    Show answer
    Start at the need, not at the door. Ask why people prop it. Perhaps staff carry proofs between the lobby and production all day, and badging with full hands is a nuisance. That is a need the first interviews missed. Possible answers: unlock that door on a schedule during working hours while reception is staffed, with door 6 and the stair door still controlled; add a held-open alert at reception; or move the boundary so that the lobby side is inside the staff layer. Each choice goes back through requirements, the door schedule and the review. A system people work round is telling you the design and the daily routine disagree.

    You have finished System Design and Integration. The next course, Installation, Commissioning and Maintenance, picks up where the documents leave off.