PanelSimulator Academy

System Design and Integration, lesson 11 of 12

Design review

Every design contains mistakes. The only question is when they are found. A design review is a planned hunt for them while they are still lines on paper. This lesson shows you who should look, what to look for, and how to make sure every finding is dealt with.

About 14 minutes. Read Drawings: plans, risers and schedules and Writing a specification first.

One mistake, three endings

The mistake: a camera cable drawn 313 feet long, which is too far for copper network cable. Pick when it is caught, then play or step through. The hours are an illustration, not a measurement.

Work to put it right, if found here !

The everyday picture

You have written an important letter. You read it through and it looks fine. A friend reads it and finds a missing word in the second line. You had read that line five times. Your eyes saw what you meant to write.

Designers have the same blindness about their own drawings. That is why the person who drew the design is the worst person to check it alone, and why a second pair of eyes is not an insult. It is the cheapest tool in the trade.

The panel above shows why the timing matters. A wrong line on a drawing costs an hour to redraw. The same wrong line, once it has become cable in a ceiling, costs days.

What a review is

A design review is a planned check of the drawings, schedules, counts and specification by people other than the designer, before money is committed. It has three features that separate it from a quick glance.

  • It is planned. The reviewers get the documents a few days ahead, with a date by which comments are due.
  • It is written down. Each problem becomes a numbered finding with an owner.
  • It is closed. The design is not released until every finding has been fixed or knowingly accepted.

On larger projects, reviews are commonly held more than once, for example when the design is roughly a third done, two thirds done and nearly complete. Early reviews catch wrong directions. Late reviews catch wrong details. On a small job a single review before ordering is enough, but it must happen.

Who reviews what

No single reviewer sees everything. Each one below reads the same documents and notices different problems.

ReviewerReads forTypical catch
Another designerSums, limits, consistency between documentsPower supply too small. Plan and schedule disagree.
Lead installerWhether it can be built as drawnNo way to get cable into that wall. Camera cannot be reached without a lift.
Customer's security or facilities managerWhether it does what they asked, and whether they can run itThe side gate everybody really uses is not on the plan.
Customer's IT staffNetwork, addresses, accounts, updatesCameras drawn on a network that is not allowed to carry them.
Authority having jurisdictionExit routes, fire doors, fire alarm linksA locked door on an exit route with no approved release.
Other tradesClashes with their own workThe cabinet is where the electrician planned a panel.

The review by the authority is not optional for anything that touches a way out. Getting out: egress and life safety in the Access Control course explains why. Book it early, because it can take weeks.

Seven questions to ask

A reviewer who simply "looks over" a design finds spelling mistakes. A reviewer who reads it seven times, with one question each time, finds real problems. Each question is a lesson you have already studied.

QuestionHow to check it
1. Does every must-have requirement have something that delivers it?Go down the requirements list. Point to the device, clause or setting for each one.
2. Does every device have a reason?Go down the schedules. Point to the requirement behind each row.
3. Can everybody get out, always?Trace each exit route on the plan with a finger. Stop at every door.
4. Do the sums work?Recheck current, battery hours, voltage drop on the longest lock run, cable lengths, switch ports and watts, storage days.
5. Do the documents agree?Compare counts on plans, schedules, bill of materials and specification. Check device numbers match everywhere.
6. Can it be built and maintained?For each device, ask how the cable gets there and how a technician reaches it in five years.
7. What happens when a part fails?Point at each box on the riser diagram, as in Designing for growth and failure.

The first two questions together are called traceability. Many designers keep a simple table for it, with requirements down the side and the design elements that satisfy them alongside. An empty cell in either direction is a finding.

Check yourself

Who is most likely to notice that a camera on the plan cannot be reached for cleaning without hiring a lift?

Walk the scenarios

Checklists catch errors in the parts. They are weaker at catching errors in how the parts work together. For that, use a walk-through: sit round the plan with the customer and act out real events, minute by minute.

  • An ordinary morning. The first employee arrives at 6:40. Which door? Is the alarm set? What do they do, in order?
  • A delivery. The driver presses the intercom at the dock. Who answers? What can they see? How is the door released?
  • A forced door at 2 a.m. Which sensor notices? Who is told? Which camera shows it, and is there light?
  • A fire alarm. Which doors release? Can people in the stairs get back onto a floor?
  • A power cut. Use the answers from the previous lesson.
  • A dismissed employee. How quickly does their card stop working at every door?

Where the room goes quiet and nobody knows the answer, you have found a gap. These same scenarios later become the acceptance test in the specification.

Review these yourself

Pass it or flag it?

Each item is a line from a design. Decide whether it can pass or should be written up as a finding.

The findings log

Comments scribbled on a drawing get lost. Put every finding in a findings log: one row each, with a number, where it is, what is wrong, how serious it is, who will fix it, and how it was closed.

No.WhereFindingSeverityOwnerClosed by
1Plan, camera 14Cable run 313 ft, over the limit for copperMust fixDesignerSwitch added in dock enclosure, revision C
2Door schedule, door 6Stair door hardware not marked as fire-ratedMust fixDesignerSchedule corrected, sent to authority
3Spec 2.4"Adequate storage" cannot be testedShould fixDesignerReworded to 30 days
4Plan, lobbyReader on the hinge side of the doorShould fixDesignerMoved to latch side
5RiserNo spare switch on siteAcceptedCustomerCustomer accepts next-day replacement, in writing

Three severities are enough. Must fix means the design is unsafe, breaks a rule or will not work. Should fix means it will work but poorly or at extra cost. Accepted means the customer has been told and has chosen to live with it. That last kind is a legitimate outcome, as long as it is the customer's decision and it is in writing.

When a fix changes a drawing, the drawing gets a new revision letter and date, and the takeoff is adjusted, as you saw in Device and cable counts.

Three examples

Simple: the count that did not match

A reviewer compares the plan with the camera schedule and finds 14 symbols and 15 rows. Camera 9 had been deleted from the plan when a wall moved, but not from the schedule. It takes two minutes to find and one to fix. Without the review, the bill of materials would have carried a camera with nowhere to go, or the plan would have lacked a view the customer expected.

Medium: the installer's question

A design shows a card reader on a glass wall beside a glass door. It looks tidy. The lead installer asks one question: "Where does the cable go?" There is no frame, no hollow wall and no floor box. The choices are a surface raceway down the glass, which the architect will refuse, or a reader pedestal fixed to the floor with a cable path cut into the slab.

On paper, the pedestal is a new line in the bill of materials and a note to the builder. Discovered on installation day, it is a stopped job and an argument about who pays.

Advanced: the walk-through that found the gap

A clinic's design passes every checklist. During the walk-through the reviewer asks what happens when the cleaner arrives at 9 p.m. The cleaner's card opens the staff door. The intrusion system, though, is armed at 7 p.m. by the last nurse, and nothing in the design disarms it for the cleaner. Every night would begin with an alarm.

Each system was correct by itself. The gap was between them, which is the subject of the Integration lesson. The fix was a requirement nobody had written: a valid card from the cleaning group at the staff door disarms the cleaning areas only, and the cleaner arms them again when leaving.

From the field

  • Print the plans large and review with a pen. People see more on paper spread across a table than on a laptop screen.
  • Review against the site, not just the drawings. Take the plan back to the building and stand where each device will go.
  • Invite the person who will be on call at 2 a.m. They ask the questions about failure that nobody else asks.
  • Thank people for findings. A reviewer who is made to feel awkward will find less next time.
  • Review again after big changes. A fix can break something that passed last time.

Common mistakes

  • Letting the designer review their own work and calling it done.
  • Holding the review after the equipment is ordered.
  • Reviewing the plan and never opening the specification or the schedules.
  • Collecting comments and not tracking them to a close.
  • Leaving the authority's review until the doors are installed.

Summary

  • The same mistake costs more at every stage it survives.
  • A review is planned, written down and closed.
  • Different reviewers catch different problems. Use several.
  • Read the design once for each question, then walk real scenarios through it.
  • Log every finding with a severity and an owner. Fix it or have the customer accept it in writing.

Exercises

Answer each one yourself first, then open the answer.

Exercise 1. In the panel at the top, how many times more work does the mistake cost when caught in use than when caught at review, using the example hours?

Show answer
Fifty times: 50 hours against 1. The exact figures are an illustration. The shape is what matters. Each stage adds work that has to be undone before the fix can begin.

Exercise 2. A design has a requirement "record who enters the stockroom" and no reader or camera at the stockroom door. Which of the seven questions catches this?

Show answer
Question 1: does every must-have requirement have something that delivers it? Going down the requirements list, the reviewer finds nothing to point to for this one.

Exercise 3. Give a severity to each: (a) a magnetic lock on an exit door with no release on fire alarm, (b) a camera label that reads "C-07" on the plan and "CAM 7" on the schedule, (c) no backup battery for the intercom, which the customer says is fine.

Show answer
(a) Must fix. It is a life safety problem and will not pass the authority. (b) Should fix. The system would work, but mismatched names cause mistakes during installation and service. (c) Accepted, once the customer's decision is recorded in writing.

Exercise 4 (think, don't memorize). The salesperson says the customer wants to sign this week and there is no time for a review. What do you say?

Show answer
A review of a small design takes a few hours, not weeks, so the choice is rarely between a review and the deadline. Offer the shortest useful version: one other designer checks the sums and the exit doors, the lead installer reads the plan, and the customer walks through three scenarios with you. If even that is refused, say plainly what is unchecked and put it in writing, especially anything touching exits. The panel at the top is your argument: an hour now against days later.