PanelSimulator Academy

System Design and Integration, lesson 9 of 12

Writing a specification

Drawings show where things go. A specification says, in words, what those things must do and how well the work must be done. Written well, it lets three companies price the same job and lets the customer compare their prices fairly. This lesson shows you how to write one that can be priced, built and tested.

About 15 minutes. Read Requirements and priorities and Drawings: plans, risers and schedules first.

One clause, three bids

Pick a way of writing the clause, then play or step through it. Prices are shown as an index, with the lowest bid at 100.

Section 28, video Clause 2.3, entrances

The everyday picture

Ask three builders to price "a nice kitchen". One imagines laminate counters and keeps your old appliances. One imagines stone and a new oven. One imagines moving a wall. Their prices differ by a factor of three, and you still have no idea which builder is the best value, because they priced three different kitchens.

Now hand each builder the same drawing and the same written list: this counter material, this many cabinets, appliances supplied by you, finished by this date. The prices land close together. The difference between them now means something.

That written list is a specification. Its first job is to make sure everyone is pricing the same kitchen.

What a specification is

A specification, usually shortened to spec, is the written half of a design. It travels with the drawings, and together they form the documents a contractor bids on and is later held to. A simple rule divides the work between them.

QuestionAnswered by
Where is it, and how many are there?Drawings and schedules
What must it do, and how well?Specification
How must it be installed, tested and handed over?Specification
Who does what, and what is left out?Scope of work, usually the first part of the specification

Say each thing once, in one place. If the drawing says 14 cameras and the spec says 16, the bidders will each choose the number that suits them, and the argument arrives after the contract is signed.

Every clause should trace back to a requirement from the lesson Requirements and priorities. A clause with no requirement behind it is a cost with no reason. A must-have requirement with no clause is a promise nobody has been asked to keep.

Three ways to say what you want

There are three common ways to write a clause. The panel at the top shows what each does to the bids.

  • Performance Says what result is wanted and how it will be measured. Bidders choose the product. Good for anything where the outcome matters more than the brand.
  • Prescriptive Says what the thing is: its type, material, rating or size. Good for cable, enclosures, door hardware and anything that must match what is already there.
  • Proprietary Names one maker and model. Sometimes necessary, for example when adding doors to an existing system. Otherwise it removes competition.

Most real specifications mix the three. A common middle path names a product as the basis of design and adds the words "or approved equal". This tells bidders the standard to meet, lets them propose another product, and makes them prove it is as good before it is accepted.

Whichever style you use, a clause is only useful if somebody can check it. "High quality images" cannot be checked. "A face in the doorway shown at 40 pixels per foot or more, by day and by night" can be checked with a test chart and a tape measure. The pixel figure here is an example. The Video Surveillance course explains how to choose it for each view.

Check yourself

Which of these clauses could an inspector test on handover day?

The parts of a section

In United States construction, specifications are usually organized by a numbering system called MasterFormat, in which Division 28 covers electronic safety and security. Each system gets a section, and each section has three parts. Even on a small job with a five-page spec, the same three parts keep you from forgetting things.

PartWhat it coversTypical contents for a security system
1. GeneralThe rules of the jobScope of work, related work by others, submittals, installer qualifications, warranty, training, record documents
2. ProductsWhat is to be suppliedPerformance and features of each device, cable types, enclosures, software and licenses, spare parts
3. ExecutionHow the work is done and provedMounting heights, cable support and labeling, firestopping, programming, testing, handover

A few terms from Part 1 deserve a line each.

  • Scope of work. A plain statement of what the contractor will do, and just as important, what is excluded or done by others. "Power outlets at each cabinet by the electrical contractor."
  • Submittals. Data sheets, shop drawings and samples that the contractor sends for approval before ordering. This is the last cheap moment to catch a wrong product.
  • Acceptance test. A written test, witnessed by the customer, that every device and every function must pass before the job is called complete.
  • Record documents. Drawings corrected to show what was really built, with schedules, settings and backups. Often called as-builts.

The words that carry the weight

Specifications use a small, strict vocabulary. "Shall" marks something the contractor must do. "Provide" is usually defined at the front to mean supply and install, complete and working. Words like "should", "may", "adequate", "as required" and "etc." invite each bidder to decide what they mean. Use one name for each thing throughout. If a "reader" on page 3 becomes a "card station" on page 9, someone will price two different items.

Write a clause

Pick a subject and a style. Read the clause, then read how it would be checked on handover day.

Same subject, four ways

How it is checked
What bidders will do

Making bids comparable

A clear spec gets you most of the way. A few more tools make the prices line up side by side.

  • A bid form. Give every bidder the same table to fill in: a price for each system, and a total. Do not let each company invent its own layout.
  • Unit prices. Ask for the price to add or remove one camera, one door, one detector. When the customer later wants two more doors, the price is already agreed.
  • Alternates. Optional items priced separately, such as "Alternate 1: add card access to the loading dock". These come straight from the should and could lists.
  • Questions in writing. Bidders send questions by a set date. Each answer goes to every bidder in a numbered addendum, so that nobody prices from private information.
  • A site walk for all bidders, together, so everyone sees the same ceilings and the same loading dock.
  • The cost of the years after. Ask for licenses, subscriptions and a service agreement to be priced for a stated period, commonly three or five years. A low price today can hide a high one later.

Three examples

Simple: thirty days

A shop owner's request for prices says "cameras with recording". Two quotes arrive. One records for 7 days and one for 30. The 7-day quote is cheaper and wins. Three weeks after a theft is noticed, the video is gone.

The fix is one sentence: "The system shall retain recordings from all cameras for at least 30 days at the stated frame rate and resolution." Now both bidders size their storage for the same thing.

Medium: or approved equal

A school district already runs one access control system across nine buildings. The spec for a tenth building is written as pure performance. The low bidder proposes a different system that meets every clause. The district would now have two sets of software, two card databases and two sets of spare parts.

The requirement that mattered, "must work as part of our existing system", was never written down. The fix is to say so: name the existing system, require new controllers and readers to be managed by it, and allow other products only if the bidder demonstrates that. Proprietary clauses have a proper place, and this is it.

Advanced: the test nobody defined

A spec says "the contractor shall test the system". On handover day the installer shows that every camera has a picture and every door opens with a card. Two months later the customer finds that doors do not release on fire alarm in one wing, and that a door held open raises no alert. The installer points out, correctly, that the system was tested.

The spec needed an acceptance test with a list: every door in every state, including forced, held, power off and fire alarm; every camera checked against its stated view by day and by night; every alarm point tripped and seen at the monitoring station; 30 days of recording confirmed before final payment. What the spec does not ask to be proved will not be proved.

From the field

  • Read every clause as a bidder looking for the cheapest honest reading. If two readings exist, rewrite it.
  • Write the acceptance test while you write the clauses. If you cannot think how to test a clause, the clause is not finished.
  • Do not copy a maker's data sheet into a spec. You will copy features that only one product has, without meaning to.
  • List what the customer will provide: network ports, addresses, a server room, an escort, a place to store materials.
  • Number every clause, so that questions, answers and test results can point to it.

Common mistakes

  • Words that cannot be tested: adequate, suitable, high quality, state of the art.
  • Saying the same thing on the drawing and in the spec, with two different numbers.
  • Naming a brand when the real need is a result, or naming a result when the real need is a match with what exists.
  • Leaving out the work between trades: power, door hardware, the fire alarm relay, the network.
  • No acceptance test, no training, no record documents.

Summary

  • A specification says what the system must do and how the work must be done and proved.
  • Its first job is to make every bidder price the same thing.
  • Write results you can measure. Name products only where a match is truly needed.
  • General, Products, Execution: three parts that keep a section complete.
  • A bid form, unit prices, alternates and written answers make prices comparable.

Exercises

Answer each one yourself first, then open the answer.

Exercise 1. In the panel at the top, which way of writing the clause gives prices that are close together and also lets bidders choose their own product?

Show answer
The measurable result. All three bidders price four cameras that must pass the same test, and their prices fall within about ten percent. Naming a model also gives close prices, but every bidder is buying the same product from the same maker.

Exercise 2. Rewrite this so it can be tested: "Provide sufficient battery backup for the access control system."

Show answer
One good version: "On loss of mains power, the access control system shall continue to operate all doors normally for at least 4 hours. Demonstrate by switching off the supply circuit during the acceptance test." The number of hours comes from the customer's requirements. The second sentence says how it will be proved.

Exercise 3. A sentence about mounting height of card readers: does it belong in Part 1, Part 2 or Part 3?

Show answer
Part 3, Execution. It describes how the work is installed, not what the product is. The reader's features belong in Part 2.

Exercise 4 (think, don't memorize). Three bids arrive for the same spec. Two are close together. The third is 30 percent lower. What do you do before recommending it?

Show answer
Find out why. A bid far below the others usually means something was left out or read differently. Compare the bid forms line by line and look for a system priced much lower. Check the counts against the drawings. Ask the bidder, in writing, to confirm that specific items are included: the acceptance test, the licenses, the night work. If the low price survives those questions, it may simply be a good price. If it does not, you have saved the customer from a job that would have been made up later in change orders or shortcuts.