System Design and Integration, lesson 8 of 12
Estimating labor and cost
The bill of materials tells you what to buy. It does not tell you how long the work will take, and time is where most estimates go wrong. This lesson gives you a method for turning counts into hours, hours into cost, and cost into a price, along with a list of the items that are easiest to leave out.
Build the hours for one small job
The job is the small building from the last lesson: 6 cameras, 4 doors, 3 motion detectors and 13 cable runs. Change the conditions and watch the hours. The figures are teaching examples, not a standard.
The everyday picture
Ask a painter to quote for your living room. The paint is the easy part: so many square feet, so many gallons. What the painter is really judging is time. Is the furniture still in the room? How much edge is there to mask? Is the ceiling ten feet up, so that every stroke needs a ladder?
Two rooms that need the same paint can need very different days. Security work is the same. Two jobs with the same bill of materials can differ by half again in hours, and hours are usually the largest thing you can get wrong.
What a price is made of
Every price, however it is presented to the customer, is built from the same layers. Work from the top of this table down.
| Layer | What goes in it | Where the number comes from |
|---|---|---|
| Materials | Everything on the bill of materials, plus freight and sales tax where they apply | Your takeoff, priced by your suppliers on the day |
| Labor | Hours multiplied by an hourly rate | This lesson |
| Subcontractors and rentals | Electrician, locksmith, fire alarm company, lift hire | Their written quotes |
| Other direct costs | Permits, inspection fees, travel, parking, software subscriptions for the first term | The authority, the vendor, your own records |
| Overhead | The cost of running the company: office, vehicles, insurance, estimating time | A percentage your company sets |
| Contingency | An allowance for what you cannot yet see | A percentage that reflects how well you know the site |
| Profit | What is left after every cost | A percentage your company sets |
The first four layers together are the direct cost: money spent because this job exists. This lesson does not quote prices for equipment. They change from month to month, so get them fresh from your suppliers every time.
Labor units
You cannot estimate "the installation" as one lump. You can estimate one small task done many times. A labor unit is the time one task takes under normal conditions, including fetching the part, laying out the position, doing the work and tidying up.
Multiply each count from your takeoff by its labor unit and add the results. The table below does this for the small building in the panel at the top. The units are examples chosen for this lesson. Your own will differ.
| Task | Labor unit, hours | Count | Hours |
|---|---|---|---|
| Pull and support one cable run | 1.0 | 13 | 13.0 |
| Terminate and test both ends of a run | 0.5 | 13 | 6.5 |
| Mount and aim a camera | 1.0 | 6 | 6.0 |
| Fit out a door: reader, strike, door contact, exit sensor | 4.5 | 4 | 18.0 |
| Mount a motion detector | 0.75 | 3 | 2.25 |
| Build and wire the cabinet | 8.0 | 1 | 8.0 |
| Program and set up the systems | 8.0 | 1 | 8.0 |
| Test every device, train the customer, hand over records | 7.0 | 1 | 7.0 |
| Field hours | 68.75 |
Where do labor units come from? The best source is your own finished jobs. Record the hours each job really took, divide by the counts, and your units improve every time. Published labor unit manuals exist for electrical and low-voltage work and make a fair starting point for a new company.
The hours nobody sees
Field hours are not the whole story. Somebody orders the materials, attends the site meeting, chases the electrician and answers the customer's questions. Many estimators add this project management time as a percentage of field hours. This lesson uses 15 percent as an example: 68.75 hours becomes about 79.
To turn hours into days, divide by the size of the crew and the length of the day. Two people working eight hours make 16 hours a day, so 79 hours is about five days. Be honest about the day. Driving to site, unloading, signing in and clearing up all come out of it.
Conditions change the hours
A labor unit assumes normal conditions: a ceiling you can reach from a stepladder, with tiles that lift out, in a building you can work in freely. When the site is different, multiply the affected tasks by a condition factor. Try the buttons in the panel at the top.
- Hard ceilings. With no tiles to lift, cable has to be fished between access points. Pulling takes longer, and somebody has to cut and patch the access holes.
- Height. Above about 12 feet a stepladder is no longer enough. Work from a lift is slower, and the lift has to be hired, delivered and collected.
- Occupied buildings. You work round people, protect their desks, and clean up every evening.
- Restricted hours. Night or weekend work is slower to start and stop, and usually carries a higher hourly rate.
- Escorts and sign-in. On secure sites, waiting for an escort can take an hour out of every day.
The site survey is where you learn which factors apply. An estimate made without one is a guess about conditions.
Check yourself
A job costs you 10,000 dollars in total. Your company wants a 20 percent margin. What price do you quote?
From cost to price
Once you have the hours, the rest is arithmetic, done in a fixed order.
- Labor cost is hours multiplied by the burdened rate. That is the wage plus everything the company pays on top of it: payroll taxes, insurance, benefits, the vehicle and tools. It is always well above the wage on the paycheck.
- Direct cost is materials plus labor plus subcontractors, rentals and other direct costs.
- Overhead and contingency are added as percentages. Contingency should be small when you have surveyed the site well, and larger when you have not been allowed above the ceiling.
- Price is total cost divided by one minus the margin.
That last step trips up many people. Markup is profit as a share of cost. Margin is profit as a share of price. They are not the same number. Add 20 percent to a cost of 10,000 dollars and you get 12,000. The profit is 2,000, which is only 16.7 percent of the price. For a true 20 percent margin, divide by 0.80 to get 12,500.
Build a price
Put in your own figures. The starting numbers are round placeholders, not real prices.
The things people forget
Estimates rarely fail because a camera was priced wrongly. They fail because something was never on the sheet. Read this list against every estimate before it leaves your desk.
- Permits and inspections, and the time spent waiting for the inspector.
- The electrician. Power supplies and cabinets need an outlet or a circuit, and somebody licensed has to provide it.
- Door work. Cutting a frame for a strike, fitting a power transfer hinge or replacing a closer may belong to a locksmith or door hardware installer.
- The fire alarm company, for the relay that releases doors when the alarm sounds.
- Lift hire, with delivery and collection.
- Firestopping of every rated wall and floor the cable passes through.
- Patch and paint after access holes and surface raceway.
- Network time. The customer's IT staff, or yours, must set up switch ports and addresses.
- Training, record drawings and the handover folder.
- Warranty visits in the first year, and licenses or subscriptions that renew.
Three examples
Simple: the small building, normal conditions
With lift-out tiles and an empty building, the table gives 68.75 field hours. Fifteen percent for management brings it to 79. A two-person crew needs five days. The estimator books the crew for a week and tells the customer so.
Medium: the ceiling nobody looked at
The same job is priced from drawings alone. On the first morning the crew finds that the corridor ceiling is plasterboard with no access. Pulling 13 runs was estimated at 13 hours. Fishing cable between cut openings takes half as long again, about 19.5 hours, and the openings then need patching and painting by someone else.
The cause was not a bad labor unit. The unit was right for a ceiling with tiles. The fix belongs in the survey: note the ceiling type in every area, and apply a factor to the tasks it affects before the price goes out.
Advanced: markup mistaken for margin
A company's owner asks for a 25 percent margin on every job. A new estimator totals a job at 80,000 dollars of cost and adds 25 percent, quoting 100,000. The profit is 20,000, which is 20 percent of the price, not 25.
The correct price was 80,000 divided by 0.75, which is 106,667 dollars. The difference of 6,667 dollars on this job is repeated on every job the estimator prices that year. The fix is to write the formula into the estimating sheet once, so that nobody works it out by hand.
From the field
- Keep a job diary. Hours estimated against hours used, task by task. It is the only way labor units get better.
- Ask the lead technician to read the estimate before it goes out. They will spot the missing lift in ten seconds.
- Write down what is excluded. "Power outlets by others. Patching and painting by others." If it is not written, the customer will assume it is included.
- Put a date on supplier prices and say how long your quote is valid.
- Price the first and last day honestly. Mobilizing, unloading, final cleaning and collecting the lift are real hours.
Common mistakes
- Estimating labor as a flat percentage of materials. Expensive cameras do not take longer to mount than cheap ones.
- Using the paycheck wage in place of the burdened rate.
- Applying normal labor units to a site that is anything but normal.
- Confusing markup with margin.
- Using contingency to cover a survey that was never done.
Summary
- Hours come from counts multiplied by labor units, task by task.
- Condition factors adjust the tasks a difficult site affects.
- Add the unseen hours: management, travel, setup and cleanup.
- Cost is materials, labor, subcontractors and other direct costs, then overhead and contingency.
- Price is cost divided by one minus the margin. Margin and markup are different numbers.
Exercises
Answer each one yourself first, then open the answer.
Exercise 1. A job has 20 cable runs. Pulling a run is 1.0 hour and terminating it is 0.5 hours. The ceiling is hard, so pulling carries a factor of 1.5. How many hours of cable work?
Show answer
Exercise 2. Field hours come to 120. Add 15 percent for management. How many days does a two-person crew need, working eight-hour days?
Show answer
Exercise 3. Total cost is 45,000 dollars and the company wants a 25 percent margin. What is the price, and what markup is that?
Show answer
Exercise 4 (think, don't memorize). The customer likes your design and asks you to take 10 percent off the price. What are your honest options?