Device and cable counts

A finished plan shows where everything goes. It does not yet say how much of everything to buy. This lesson shows you how to count devices off a plan, measure the cable honestly, and turn both into a bill of materials that nobody has to top up halfway through the job.

About 15 minutes. Read Drawings: plans, risers and schedules first.

Take off a plan

Pick a job, then play or step through it. The sheet on the right fills in as you go.

IT room Office Lab Lobby Storage corridor cabinet +8 up +2 down +10 slack +3 slack C C C C C C R R R R M M M C camera R card reader M motion detector the building is about 100 feet wide Takeoff sheet nothing counted yet

The everyday picture

You are cooking for thirty people from a recipe written for four. You do not walk round the shop guessing. You go down the recipe line by line, multiply each amount, and write a list. Then you add the things the recipe never mentions: foil, salt, a second tray.

A security plan is the recipe. The list you write from it is called a bill of materials, or BOM. Guess it, and the job stops on day three while somebody drives to a supplier for forty feet of cable and a box of connectors.

Three counts

Estimators call this work a takeoff, because you take quantities off the drawing. It is really three counts, done in this order.

  • Devices Everything with a symbol on the plan: cameras, readers, locks, detectors, intercom stations. You count these directly.
  • Cable One run for each device, measured along the real route, with the parts a flat plan hides added on.
  • Everything they land on Controller ports, switch ports, panel zones, licenses, power and the small parts. These are worked out from the first two counts.

Counting devices

Counting sounds too simple to need a method. It needs one, because a miscount of two cameras on a forty-camera plan is easy to make and expensive to discover.

  1. Write the drawing number, revision and date at the top of the sheet. If the plan changes, you will know which version you counted.
  2. Count one kind of device at a time, one sheet at a time. Do not try to count cameras and readers in the same pass.
  3. Mark each symbol as you count it. On paper, use a highlighter with one color for each kind. On a screen, use the count tool in the drawing software. Any symbol left unmarked at the end has been missed.
  4. Check the count against the schedules. The door schedule and camera schedule from the drawings lesson list every door and camera by number. If the plan shows 14 cameras and the schedule lists 15, one of them is wrong, and you want to know now.

The result is a takeoff sheet. For the small building at the top it looks like this.

DeviceSymbolCount from planCount from scheduleAgreed
CameraC66Yes
Card readerR44Yes
Motion detectorM33Yes

Check yourself

A ruler on the plan says a camera is 105 feet from the cabinet. How much cable should you allow for it?

Measuring cable

Cable does not travel in straight lines. It follows corridors, turns at right angles, climbs into the ceiling and comes down again. A straight ruler line across the plan is always too short. Measure each run in four parts.

Part of the runHow you get itFar camera in the plan above
Route on the planMeasure along the path the cable will really take, using the plan's scale25 + 90 + 30 = 145 ft
Rise and dropHeight from the cabinet up to the cable path, and from the path down to the device8 + 2 = 10 ft
SlackA spare loop left at each end for making off the cable and for later repairs10 + 3 = 13 ft
This run168 ft

The spare loop is called a service loop. Ten feet at the cabinet and three feet at the device is a common allowance. Use your company's standard if it has one.

Add every run of the same cable type together, then add a waste factor. Ten percent is usual. It covers the short tail left in the bottom of every box, the run that has to go round a duct nobody drew, and the piece damaged by another trade.

Then round up to whole boxes. Network cable is commonly sold in 1,000-foot boxes or reels. A total of 3,200 feet means four boxes, not three and a bit.

Two limits to check while you measure

  • Network cable. A copper Ethernet run is limited to 100 meters, which is 328 feet, from switch to device. That figure includes the patch cords at each end, so the cable fixed in the building should stay within about 295 feet. Any run that measures longer needs a different answer: a switch closer to the device, or fiber.
  • Power cable. A long run to a lock loses voltage. Cable and wiring in the Access Control course shows the sum. Flag every lock run over about 150 feet for that check.

Cable calculator

Early in a job you may not have time to measure every run. An average gives a fair first figure. Before you order, measure every run and list it in a cable schedule.

One cable type, many runs

Lengths are in feet. The last field is the longest single route on the plan, used to check the network cable limit.

average run, all four parts
all runs, before waste
to order, with waste
boxes of 1,000 feet

What each device brings with it

A camera on the plan is one symbol. On the job it is a camera, a mount, a cable, two connectors, a port on a switch and often a recording license. Think of each device as a small kit. Estimators call that kit an assembly. Write the kit down once, and every count multiplies through it.

One of theseUsually bringsAnd uses up
CameraMount or back box, network cable, a connector at each end, patch cordOne switch port with power, recording storage, perhaps a license
Controlled doorReader, lock, door contact, exit sensor, cable to each, suppressor at the lockOne controller door port, lock power
Motion detectorAlarm cable, end-of-line resistorOne zone on the intrusion panel
Intercom stationBack box, network cableOne switch port with power, a license on some systems

Count the cabinet last, because its size is the sum of everything that lands on it. In the plan above, six cameras, the door controller, the recorder and the link to the building network need nine switch ports. That will not fit an 8-port switch. The lesson Designing for growth and failure covers how much spare to add on top.

Finally, list the parts that have no symbol at all: cable hangers every four to five feet along the route, anchors and screws, firestop sealant for every rated wall the cable passes through, labels, and conduit where cable is exposed. They are small, and a job cannot finish without them.

Three examples

Simple: one camera, measured honestly

A technician prices a single extra camera by laying a ruler on the plan: 105 feet. On the day, the cable follows the corridor, climbs 8 feet at the cabinet and needs slack at both ends. It uses 168 feet, which is 60 percent more. On one camera that is a small annoyance. On forty it is a second order and a lost day. The fix is to measure the route, not the gap.

Medium: the camera at the far end of the warehouse

A warehouse design has 16 cameras cabled back to one cabinet in the front office. The routes on the plan add up to 2,240 feet. Each run adds 10 feet of rise and drop and 13 feet of slack, so 16 runs add 368 feet, for 2,608 feet. Ten percent waste brings that to about 2,870 feet, so the order is three boxes.

While measuring, the estimator notices that the camera over the last dock door has a route of 290 feet. With its 23 feet of rise, drop and slack it comes to 313 feet, which is over the limit for copper network cable. The fix is made on paper: a small switch in a locked enclosure halfway down the warehouse, fed by fiber. Found during the takeoff, it is a line on a drawing. Found during testing, it is a camera that drops out and a lift hired twice.

Advanced: the plan changed after the count

An estimator counts 31 cameras from the plans and the order is placed. On site, the installers find 34 symbols on their copy. The architect had moved a wall and the designer added three cameras in revision C. The count was made from revision B.

Nothing was miscounted. The sheet simply did not say which drawing it came from. The fix is a habit: put the drawing number, revision and date on every takeoff sheet, and when a new revision arrives, count only the changes, which a good designer marks with a cloud, and adjust the sheet.

From the field

  • Check the scale before you measure. A plan printed "to fit the page" is no longer at the scale in its title block. Measure a doorway you know is about 3 feet wide and see what the ruler says.
  • Count twice, on different days if you can. If the two counts differ, count a third time.
  • Keep cable types separate. Network cable, composite door cable and alarm cable each get their own total and their own waste.
  • Remember that boxes get shared out. A crew pulling four cables at once needs four boxes open, even if the total would fit in three.
  • Give every run a number on the cable schedule. The same number goes on the label at both ends.

Common mistakes

  • Measuring cable in a straight line from cabinet to device.
  • Forgetting the height of the building. In a warehouse with a 30-foot roof, rise and drop can be longer than the route.
  • Counting devices and forgetting the ports, zones and licenses they need.
  • Counting from an old revision of the plan.
  • Leaving out the parts with no symbol: hangers, firestop, labels, connectors.

Summary

  • A takeoff turns a plan into quantities. Count devices, then cable, then what they land on.
  • Count one kind at a time, mark each symbol, and check against the schedules.
  • A cable run is route plus rise and drop plus slack. Add waste, then round up to whole boxes.
  • Check long network runs against the 100-meter limit while you measure.
  • Every device is a kit of parts, and the cabinet is sized from the totals.

Exercises

Answer each one yourself first, then open the answer.

Exercise 1. In the plan at the top, step through "Measure one cable". By how many feet does the real run exceed the straight line, and which part adds the most?

Show answer
The real run is 168 feet against 105, so 63 feet more. Following the corridor adds the most: 145 feet of route against 105 in a straight line, a difference of 40 feet. Slack adds 13 and rise and drop add 10.

Exercise 2. Ten camera runs average 90 feet on the plan. Each has 10 feet of rise and drop and 13 feet of slack. With 10 percent waste, how many 1,000-foot boxes do you order?

Show answer
Each run is 90 + 10 + 13 = 113 feet. Ten runs are 1,130 feet. With 10 percent waste that is 1,243 feet, so two boxes. The calculator will confirm it.

Exercise 3. A design has 9 controlled doors and uses four-door controllers. How many controllers, and how many door ports are left spare?

Show answer
Three controllers, giving 12 ports, with 3 spare. Two controllers give only 8 ports, which is one short.

Exercise 4 (think, don't memorize). Your manager says, "Don't measure it. The last office job this size used 6,000 feet, so order that plus a bit." When is that reasonable, and when is it not?

Show answer
It is reasonable for a first budget figure, before drawings exist, as long as everyone knows it is rough. It is not good enough for an order. Two offices of the same floor area can differ greatly: where the cabinet sits, how high the ceiling is, and how many devices are at the far end all change the total. The past job is a useful check on your measured figure. If your takeoff says 3,000 feet and the last similar job used 6,000, find out why before you order either amount.