PanelSimulator Academy

System Design and Integration, lesson 2 of 12

The site survey

Lesson 1 turned the customer's first sentence into a list of things the system must do. Now you have to see where it will live. A floor plan shows where the walls were meant to be. A site survey shows what is really there: the door that does not latch, the ceiling you cannot open, the closet with no spare outlet. This lesson gives you a routine for the visit.

About 15 minutes. Read lesson 1, From need to design, first.

Walk the building

Pick a numbered stop, here or on the drawing, to see what a surveyor records there.

air duct power panel outside lobby fire-rated wall equipment room space above the ceiling planned cable route
Measure
    Photograph
      Ask

        The everyday picture

        Two moving companies quote for the same house. The first asks on the phone how many bedrooms you have and names a price. The second sends someone who walks through, opens the attic hatch, notices the piano and measures the turn in the stairs.

        On moving day the first company discovers the piano. You discover what "additional charges" means. The second company's price was right because somebody looked.

        A site survey is that walk-through. Lesson 1 gave you the needs and requirements. The survey tells you what the building will allow, and what it will cost to do there.

        Before you go

        A survey goes badly when you arrive and the closet is locked, the only plans are in an email, and nobody may lift a ceiling tile. Arrange these first:

        • Plans. Ask for floor plans and print two copies, one to mark and one clean. If there are none, the fire evacuation map on the wall is a start.
        • An escort with keys, ideally the person who looks after the building. They know which closet floods and which wall was added last year.
        • Permission to open ceilings, enter electrical and network rooms, and take photographs. Some sites forbid cameras in some areas.
        • The site's safety rules. Ask what protective equipment is required, and ask whether the building has been checked for asbestos before you disturb any ceiling or pipe covering in an older building.
        • The requirements from lesson 1, so you know which doors and areas matter.
        BringFor
        Tape measure and a laser distance meterDoors and frames by tape. Rooms, corridors and ceiling heights by laser.
        Phone or camera, fully chargedMore photographs than you think you need.
        Flashlight and a 6-foot stepladderLooking above ceilings and at the tops of door frames.
        Marked-up plans, clipboard, pens in two colorsOne color for what exists, one for what you propose.
        MultimeterConfirming that an outlet or an existing supply is live, and at what voltage.
        A survey form with one line per doorSo that the tenth door gets the same questions as the first.

        The order of the walk

        Walk from the outside in, the way an intruder or a visitor would. Access Control lesson 14 called these the layers. Following them keeps you from skipping a side door or a shared stairwell.

        1. The boundary and grounds. Fences, gates, parking, lighting poles, places where a camera could be mounted and what it would see.
        2. Every way in. Each exterior door, dock door, roof hatch and ground-floor window that opens. Count them. The number on the plan is often wrong.
        3. The lines inside. Doors between public and staff areas, and the rooms that hold what is being protected.
        4. The equipment rooms. Where cabinets, recorders and network switches can live, and what power and cooling are there.
        5. The paths between. Ceilings, risers between floors, and every wall the cable must cross.

        Before trusting a plan's scale, measure one long wall with the laser and compare it with the drawing. A plan that has been photocopied or printed to fit the page can be off by a tenth or more.

        If the design includes outdoor cameras, come back after dark. The parking lot that looks evenly lit on the plan has a black corner behind the dumpster. Note which way each entrance faces as well: a camera looking out through an east or west door stares into the low sun for part of every day.

        Check yourself

        Which of these can you learn only by visiting?

        What to record at a door

        Doors take the most time and repay it. Each line below becomes a column in the door schedule from Access Control lesson 14.

        RecordWhy it matters
        Clear width and height, and door thicknessHardware is ordered to fit. Most commercial doors are 1¾ inches thick, but check.
        Door and frame materialWood, hollow metal, aluminum and glass each take different locks and different labor.
        Hand and swingLocks and exit devices are ordered left or right.
        How it latches now, and the lock's maker and typeDecides whether a strike, an electrified lock or a magnet is possible.
        Does it close and latch by itself, ten times out of tenIf not, a closer or hinge repair goes in the price.
        Any fire label, usually on the hinge edge of the door and inside the frameA labeled door limits what may be cut or fitted. Never paint over or remove a label.
        Is it on an exit routeSets the rules for how it must open from inside. Confirm with the authority having jurisdiction.
        Wall beside the latch sideWhere the reader goes, what the wall is made of, and how cable reaches it.

        For a reader, note a mounting height the customer's accessibility rules allow. In the United States, controls that people must reach are generally kept no higher than 48 inches above the floor. Check the current accessibility standard and local code.

        Photographs that are useful later

        Fifty photographs of gray doors are worthless if you cannot tell them apart. Use a routine:

        • First shot: the room sign or door number. Every photograph after it belongs to that door until the next sign.
        • Then wide, then close. The whole door from each side, then the latch edge, the top of the frame and the wall where the reader will go.
        • Labels and nameplates. Fire labels, lock makers' marks, the labels inside electrical panels, the model of the existing recorder.
        • The view, not only the mount. For a camera position, hold the phone where the camera will be and photograph what it would see.
        • Write the door number on the plan as you go and use the same number in your notes. Lesson 6 turns those numbers into drawings.

        Measure a cable run

        Cable does not travel in the straight line you can draw on a plan. It follows corridors, turns corners, climbs into the ceiling and drops down the wall at the other end. It also needs slack at both ends so that equipment can be moved and re-terminated.

        One limit matters more than any other. Standard network cabling is designed for a total of 328 feet, or 100 meters, from switch to device, and of that about 295 feet is the installed cable. A run that looks like 240 feet on the plan can pass that limit once it is walked.

        How long is the run, really?

        Enter what you measured on site. All lengths are in feet.

        installed length
        longer than the route on the plan
        to order for this run, with 10% for waste

        For lock and sensor cable there is no single length limit. What matters there is voltage drop, which Access Control lesson 9, Cable and wiring, showed you how to work out.

        Three examples

        Simple: fifteen minutes at one door

        A customer wants card access on a stockroom door. You measure a 36-inch hollow metal door in a hollow metal frame, left hand, with a cylindrical lock. You let it close ten times. Three times it stops against the latch without clicking shut.

        That observation is worth more than every measurement. An electric strike on a door that does not latch secures nothing. The quote now includes a new closer, and the customer hears about it before the work starts, not after.

        Medium: the plan that was six years old

        The plan of an office floor shows a network closet 180 feet from a new camera. On site, the closet turns out to have become a kitchen during a remodel. The network equipment now lives at the far end of the floor.

        You walk the route with the laser: 255 feet of corridor, 12 feet up, 10 feet down and 15 feet of slack, which makes 292 feet. That is inside the limit by 3 feet, with no allowance for a detour around a beam. You record a second, safer option: a small network switch in a locked ceiling enclosure halfway along, which the customer's network staff must approve.

        Advanced: a building that cannot be disturbed

        A hospital wing needs new readers and cameras. The survey finds that the corridor ceilings may be opened only with a permit from the hospital's infection control staff, with dust barriers, and only at agreed hours. Several walls are fire and smoke barriers, and each new hole needs an approved firestop.

        None of this is visible on the floor plan, and all of it changes the design. The surveyor records which ceilings are affected, photographs the existing sleeves through each barrier and how full they are, and asks who issues the permit and how long it takes. The design then follows routes with the fewest barrier crossings, and the labor estimate includes the waiting and the barriers. A price built from the plan alone would have been short by weeks.

        From the field

        • Look above the ceiling at both ends of every route and once in the middle. The beam, duct or solid wall is always in the part you did not look at.
        • Talk to the cleaner and the receptionist. They know which doors are propped and which alarm everyone ignores.
        • Read the labels in the electrical panel and note a spare breaker, or the lack of one. Ask if the circuit is on a generator.
        • Stand where each camera will hang and look. Trees grow, signs go up and delivery trucks park in the view.
        • Type up your notes the same day. By the third day you will not remember which door had the wooden frame.

        Common mistakes

        • Pricing from a plan without visiting, or visiting without the plan.
        • Measuring cable in a straight line and forgetting the rise, the drop and the slack.
        • Surveying only in daylight for a system that must work at night.
        • Photographing everything and labeling nothing.
        • Not opening the door. A door is judged by how it closes, not how it looks.
        • Assuming there is spare power and network in the closet because there is a closet.

        Summary

        • The survey finds what plans cannot show: condition, obstructions and how people use the place.
        • Prepare first: plans, an escort with keys, permissions and the site's safety rules.
        • Walk from the outside in, then the equipment rooms, then the cable paths.
        • At every stop, measure, photograph and ask.
        • Walk each cable route. Add rise, drop and slack, and keep network runs under about 295 feet installed.

        Exercises

        Answer each one yourself first, then open the answer.

        Exercise 1. A corridor route measures 200 feet. The cable rises 14 feet at the equipment room, drops 9 feet at the camera, and you allow 15 feet of slack. What is the installed length, and is it within the limit for network cable?

        Show answer
        200 + 14 + 9 + 15 = 238 feet. That is under 295 feet, so it is fine. With 10 percent for waste you would order about 262 feet for this run. Try it in the calculator above.

        Exercise 2. Where do you look for a fire label on a door, and why should you record it?

        Show answer
        Usually on the hinge edge of the door, with a matching label on the frame. A labeled door is part of the building's fire protection. Any lock, strike or cable hole added to it must be allowed for that door, so the design and the price both depend on knowing.

        Exercise 3. The building manager says the space above the corridor ceiling is used to return air to the air handlers. What does that change?

        Show answer
        That space is a plenum. Cable run through it must be plenum-rated, which costs more than ordinary cable, as Access Control lesson 9 explained. It goes on the survey notes so that the right cable is priced and ordered.

        Exercise 4 (think, don't memorize). You have two hours on site, not the four you planned. What do you survey first, and what do you leave?

        Show answer
        Start with what is hardest to guess and most expensive to get wrong: the doors that will be controlled, the equipment room, and the longest or most awkward cable route, including one look above the ceiling. Take the photographs with room signs so they can be sorted later. Leave what can be answered by phone or from the plan, such as room names and staff numbers. Tell the customer what you did not see, write it in the design as an assumption, and arrange a second visit before the price is final.