Fire Alarm Interface and Life Safety, lesson 10 of 10

Working with the fire marshal

Every lesson in this course has ended with the same advice: ask the authority having jurisdiction. This last lesson explains who that is, what to bring them, what a permit and an inspection involve, and how to make the person with the clipboard your ally.

About 13 minutes. Read the rest of this course first.

Follow one job from first question to final record

Pick a situation, then play or step through. The job is a pair of magnetic locks and one delayed exit in a store.

The everyday picture

Think of building an extension on a house. You could simply build it. But if you do, and the town later finds it sits too close to the boundary, the town can make you take it down. So people who have done it before walk into the planning office first with a sketch, ask what is allowed, and build what was agreed.

The planning officer in that story is not an obstacle. They are the one person who can tell you, before you spend the money, whether the result will be allowed to stand. The fire marshal plays that part for every door in this course.

Who the authority is

The authority having jurisdiction, or AHJ, is whoever has the legal power to approve or refuse a piece of work. It is a role, and several people may hold it on one building.

AuthorityWhat they look atYou meet them when
Fire marshal or fire prevention officeFire alarm, exits, locking on exit doors, fire department accessAlmost any job in this course
Building officialThe building code as a whole: exits, fire doors, permits, occupancyNew buildings and alterations
Electrical inspectorWiring methods, power supplies, cable typesJobs that need an electrical or low-voltage permit
Elevator inspectorEverything in and around elevatorsReaders in cars, recall
State or federal agenciesHospitals, care homes, schools, detentionControlled egress, school lockdown hardware
The owner's insurerTheir own requirements, sometimes stricter than codeLarger commercial and industrial sites

Two facts explain why you cannot simply read the code book yourself. First, each state or city adopts a particular edition of each code, often years after it is published, and adds its own amendments. The rule in the next county may differ. Second, codes need interpreting, and the interpretation that counts is the authority's. So the first questions on any job are "which editions apply here?" and "who reviews this?"

When to ask, and for what

Ask before you quote, whenever a job includes any of these:

  • a magnetic lock, or any lock that needs power to let people out,
  • delayed or controlled egress,
  • locking stair doors from the stair side,
  • any electric hardware on a fire-rated door,
  • anything connected to the fire alarm system or the elevators,
  • lockdown hardware in a school,
  • gates or doors on the route the fire department uses to get in.

A permit is written permission to do the work, issued after the authority has reviewed your plans. Whether a security job needs one varies a great deal. Some cities require a permit for every access-controlled exit door. Others only for special locking arrangements. Many states also require the installing company and its technicians to hold a license. The fire alarm contractor will have their own permit for any change on their side. Ask, and do not assume last year's town is this year's town.

Check yourself

An inspector tells you on site that a 30-second delay on an exit would be acceptable. What do you do before setting it?

What to submit

A plan reviewer has minutes for your job and has never seen the building. Give them a small, clear package that answers the questions they are paid to ask.

DocumentWhat it shows
Floor planEvery affected door, numbered, with exit routes and fire-rated walls marked
Door scheduleFor each door: its fire rating, the lock type, fail-safe or fail-secure, how people get out, and what happens on fire alarm and on power loss
Narrative, one pageIn plain words, what the system does on a normal day, in a fire alarm and in a power cut
Wiring diagramLock power supplies, the fire alarm relay and the demarcation terminals, exit sensors and buttons
Data sheetsEach lock, supply and exit device, with its listing marks visible
Battery calculationLoad and standby time for each lock supply, as "Power supplies and batteries" showed
Fire alarm contractor's letter or drawingThat the relay will be provided, where, and which alarms operate it

The door schedule does most of the work. An inspector who can read one line per door and see "lever always free, lock fail-secure, no fire alarm connection needed" will move quickly to the three doors that deserve real attention.

Inspections and corrections

After the permit comes the work, and then the inspection. On larger jobs there may be an early visit while cable is still visible, and a final one with the acceptance test from the last lesson. The inspector compares the building with the approved plans. A difference is a problem even if your change was an improvement.

If something fails, you get a written correction notice. Fix exactly what it says, tell the inspector, and expect a return visit. Three habits help:

  • Be there, with the plans and the test sheet. An inspector left to find the cabinet alone starts the visit annoyed.
  • Do not argue code on site. If you believe a correction is mistaken, ask which section it rests on, thank them, and take it up in writing through the office.
  • Never hide anything. If you know a door is not finished, say so first.

Sometimes the code's standard answer does not fit, for example in a historic building where a door cannot be altered. Codes allow the authority to accept an alternative that gives equal safety. That takes a written request, usually prepared with an engineer or architect, and a written reply. It is never settled by a nod in a corridor.

Changes after approval go back through the same door. Adding a lock, changing a lock type or moving a release from one alarm zone to another alters what was approved. Send a revised sheet before doing the work.

Fire department access

The fire marshal also cares about getting firefighters in. Your locks are in their way by design, so the building provides an agreed way past them.

  • Key box. A small locked box near the main entrance, opened by a key that only the fire department holds. Inside are the building's keys and, more and more often, an access card. When you rekey a door or change the card system, the contents of the box must be updated. Tell the owner every time.
  • Gates. Powered gates on the fire access route generally need a fire department override, by key switch or another approved method, and must be openable when power fails. The Access Control lesson on gates covered the hardware.
  • Fire command center. In tall buildings, a room near the entrance holds the fire alarm controls, the stair door release switch and the elevator status panel. Nothing of yours goes in there without approval.

One more duty belongs to the owner but often starts with you. If your work means part of the fire alarm must be switched off for a time, that is called an impairment. The owner follows a set procedure, which may include telling the fire department and posting a person to watch for fire. You ask for it in advance. You never arrange it quietly with a helpful janitor.

Who do you ask?

Six questions from real jobs

Choose who has the answer, then read why.

Three examples

Simple: the phone call before the quote

A dentist wants a magnetic lock on the glass door between the waiting room and the treatment rooms. Before pricing it you call the fire prevention office, describe the door and ask what they require. They say a permit is needed for any magnetic lock on an exit route, and list the release devices they expect. Your quote includes the permit fee, the sensor, the button and the fire alarm contractor's relay. A competitor's cheaper quote leaves all four out, and you can explain to the dentist exactly why.

Medium: the correction notice

At a final inspection the fire inspector pushes a delayed exit and times it at 15 seconds, then looks for the sign. It is on the wall beside the door, where the open door covers it. The notice reads "sign to be on the door". Nothing else failed.

You move the sign that afternoon, photograph it, and email the inspector. They pass the door from the photograph and close the permit. Arguing that the wall was "nearly the same" would have cost a week.

Advanced: one hospital, four authorities

A hospital adds a locked memory care unit. The city building official reviews the alteration. The fire marshal reviews the locking and the fire alarm changes. The state health department has its own rules for patient units, and the hospital's insurer wants to see the sprinkler coverage. Each has asked for slightly different things.

The hospital's architect leads. You supply one door schedule and one narrative that all four receive, so that nobody approves a different version. Where two authorities disagree about automatic unlocking, the architect gets them into one meeting and the stricter reading is built. Your job file ends up with four approvals, the joint test sheet and the staff training record. Five years later, when a new inspector asks why those doors are locked, the hospital hands over that file.

From the field

  • Call early and be brief. "One door, magnetic lock, office building, here is what I plan" gets a faster answer than a twenty-page email.
  • Write down the name, the date and the answer of every conversation, and confirm it by email the same day.
  • Leave a copy of the approved plans and the test sheet in the cabinet, in a plastic sleeve.
  • Learn your local amendments. After a few jobs in one city you will know its habits. Do not carry them to the next city.
  • Introduce yourself to the fire alarm contractor's project manager. Inspectors notice when two trades arrive with one story.

Common mistakes

  • Installing first and asking afterward.
  • Relying on a verbal yes.
  • Treating what one city allowed as permission in another.
  • Changing the design after approval without telling anyone.
  • Rekeying or changing cards and forgetting the fire department's key box.
  • Leaving the permit, the inspection or the fire alarm contractor's time out of the quote.

Summary

  • The authority having jurisdiction is whoever can legally approve the work. There may be several.
  • Codes are adopted and amended locally, so the answer depends on the place and the edition.
  • Ask before quoting any job that touches exits, fire doors, the fire alarm or elevators.
  • Submit a floor plan, a door schedule, a plain narrative, a wiring diagram and data sheets.
  • Get approvals and changes in writing, be present at inspections, and keep the records in the building.

Exercises

Answer each one yourself first, then open the answer.

Exercise 1. What does "authority having jurisdiction" mean, and why might a single job have more than one?

Show answer
It means whoever has the legal power to approve or refuse the work. Different officials cover different subjects: the fire marshal for exits and fire alarm, the building official for the building code, the elevator inspector for elevators, and state agencies or insurers for particular kinds of building.

Exercise 2. In the second situation at the top, at which stage is the problem found, and where does the job have to return to?

Show answer
It is found at the inspection, after the hardware is already on the doors. The job goes back to the drawings stage: plans are submitted, a permit is sought, and the work is corrected to match what is approved, at the installer's cost.

Exercise 3. Name four things a door schedule should state for each door.

Show answer
Any four of: the door number and location, its fire rating, the lock type, whether it is fail-safe or fail-secure, how people get out from inside, what happens on fire alarm, and what happens on loss of power.

Exercise 4 (think, don't memorize). A general contractor on a tight schedule tells you to fit the magnetic locks now, because "the inspector never looks at low-voltage work in this town". What do you do?

Show answer
Do not rely on it. Call the fire prevention office yourself and ask what is required for magnetic locks on those doors. It takes one phone call. If a permit is needed, tell the contractor in writing, with the time it will add, and offer what can go ahead meanwhile, such as cable and cabinets. If you install without approval and someone is later trapped or a later inspector does look, the responsibility is yours, not the person's who said nobody checks. The schedule is the contractor's problem. The exit is everyone's.