Fire Alarm Interface and Life Safety, lesson 9 of 10
Testing together
Every link in this course crosses a boundary between two trades, and a link that crosses a boundary is the easiest thing in a building to leave untested. This lesson shows how to prove it with the fire alarm company, door by door, and how to leave a record that the next person can trust.
Run the test sheet
Each row is a device the fire alarm contractor will operate. A small ring marks what the sequence of operations says should happen. Operate each row and compare.
The everyday picture
Think of two crews digging a tunnel from opposite sides of a hill. Each crew can measure its own half perfectly. The only proof that the tunnel works is the day they break through and someone walks from one end to the other.
The fire alarm contractor tests that their relay operates. You test that your locks drop when a contact opens. Neither test shows that an alarm in the building frees the door. Only an alarm, followed by a hand on the door, shows that.
Why test together
The link fails in ordinary ways, and all of them are invisible until tested:
- The relay is programmed for the wrong alarms, or follows the horns and resets when they are silenced.
- A door was added after the first test and never put on the release.
- One output switch on a power supply was left in the wrong position.
- The factory link is still across the fire alarm input.
- The fire alarm technician disables the relays during their own yearly test, to avoid upsetting the building, and so the release is never exercised at all.
The last one is common and well meant. It is why you ask for a time when the outputs are left enabled and the doors are watched.
There are two kinds of test. An acceptance test happens when the work is new or changed, often witnessed by the authority having jurisdiction. A periodic test repeats it on a schedule. Fire alarm rules generally expect these control functions to be tested regularly, commonly once a year, and again after any change to either system. The authority and the fire alarm contractor will tell you what applies.
Who is in the room
| Person | Their part |
|---|---|
| Fire alarm contractor | Operates detectors, pull stations and switches by approved methods. Silences and resets the panel. Changes the fire alarm program if a fault is theirs. |
| Building owner or manager | Sets the date. Warns occupants. Has the monitoring company place the system on test, so the fire department is not sent, and takes it off test afterward. |
| Security installer | Stands at the doors. Checks each lock, holder and reader. Reads the access system's log. Fixes faults on the security side. |
| Elevator contractor | Present whenever elevator recall is part of the test. |
| Authority having jurisdiction | Witnesses acceptance tests where required, and may ask for any part to be repeated. |
You do not trigger the fire alarm yourself. No test smoke, no heat gun, no borrowed pull station key. If the fire alarm contractor cannot attend, the test does not happen that day.
Check yourself
Which single test proves that the fire alarm will free a magnetic lock on an exit?
Before, during and after
Before
- Get the sequence of operations from the fire alarm contractor: the table of which inputs cause which outputs. Turn it into a test sheet like the one at the top, with one line for every door.
- Walk the door list. Confirm each door exists, is labeled, and closes and latches.
- Charge the lock supply batteries and fix known faults first. A test day spent on a bad closer is wasted.
- Agree radios or phones, and who stands where.
During
- Start from normal: fire panel clear, all doors locked, access system showing no alarms.
- The fire alarm contractor operates one device. You check every door on the sheet by hand, then the access log.
- They silence the horns. You check the doors again. They must not have relocked.
- They reset the panel. You check that every door has relocked and every holder can hold again.
- Repeat for each kind of input on the sheet, including one that should not release anything, such as a supervisory signal.
- Then test the failures: lift your wire at the fire alarm input, and switch off mains to each lock supply.
After
- Confirm the fire panel is normal and every disabled point has been restored.
- Confirm the monitoring company has taken the system off test.
- Walk the doors one last time. All locked, none propped.
- Sign and date the sheet, with names, and file copies with the owner and with your job records.
What to check at each door
| Kind of door | On alarm | Also check |
|---|---|---|
| Magnetic lock on an exit | Door pushes open with no card, button or sensor | Stays free after horns are silenced. Relocks only after reset. |
| Stair door needing re-entry | Stair-side lever turns freely | Door is still latched when pushed without the lever. Test from inside the stair. |
| Held-open fire door | Releases, closes fully and latches | Nothing in its path. Paired leaves close in the right order. |
| Delayed egress door | Opens at once, with no delay | On a normal day: measured delay, sounder, sign, manual reset. |
| Controlled egress door | Unlocks as the approved design says | Staff release works from every point listed in the approval. |
| Fail-secure door with free inside lever | No change expected | Lever opens the door. Outside stays locked. |
The last row matters. A good test confirms what should not happen as well as what should. If a storeroom that was meant to stay locked swings open on alarm, someone has put it on the release by mistake.
Plan the test day
A joint test takes longer than people expect, because every check means walking to a door. Count the checks first. The two minutes per check and the half hour for setup are planning figures. Adjust them for your building.
How many checks, and how long?
Three examples
Simple: the new door nobody listed
A shop adds a magnetic lock to a side exit a year after opening. The installer wires it to a spare output on the existing supply. At the next yearly test you push that door during the alarm and it holds. The spare output's switch was never set to follow the fire alarm input. One switch is moved, the door is retested with the fire alarm contractor still on site, and a line is added to the sheet.
Medium: the silent yearly test
An office building has "passed" its fire alarm test for four years. You are new to the site and ask to watch the doors during the next one. The fire alarm technician explains that they always disable the door relays first, because releasing the lobby in working hours annoys the tenants.
So the release has not been proven since the building opened. You and the building manager arrange an evening slot with the relays enabled. Two stair doors on the ninth floor stay locked: a tenant's contractor had fitted fail-secure locks during a fit-out. The owner has them replaced, and the evening test becomes a fixed yearly appointment.
Advanced: a test with four trades
A new hospital wing has released exits, stair re-entry, door holders, a controlled egress unit and elevator recall. The acceptance test is witnessed by the fire marshal.
The fire alarm contractor's sequence of operations runs to forty rows. Before the day, the trades hold a dry run without the marshal and find three faults: a holder that will not re-hold, a lock supply on the wrong relay, and a nurse-station release switch wired to one door of a pair. On the day, each trade has a person on a radio at their own equipment. The fire marshal chooses which devices to operate. Every row is initialed by the trade responsible, and the completed sheet goes into the building's records with the approval letters.
From the field
- Put a hand on every door. A green lamp on a power supply shows that an output switched. Only a push shows that a door opened.
- Test with the network unplugged once. If the release still works with the controller cut off from the server, you know it is not a software rule.
- Write down the device that was operated, by its address or label, so the test can be repeated exactly.
- Hold a dry run before any witnessed test. Inspectors remember contractors who waste their morning.
- Leave nothing bypassed. The most dangerous minute of a test day is the one after everyone has packed up.
Common mistakes
- Testing each trade's half separately and calling the link proven.
- Triggering the fire alarm yourself.
- Forgetting to place the system on test, and meeting the fire department at the front door.
- Checking the doors on alarm but not after silence and after reset.
- Testing a sample of doors and signing for all of them.
- Keeping no record, so next year's technician starts from nothing.
Summary
- The link between fire alarm and security is proven only by operating a fire alarm device and trying the doors.
- The fire alarm contractor operates and resets. The owner warns people and the monitoring company. You check doors and logs.
- The sequence of operations is the test sheet. Every row and every door gets a result.
- Check on alarm, after silence, after reset, and with a wire lifted and the mains off.
- Test when new, after every change, and on the schedule the authority requires. Keep the signed record.
Exercises
Answer each one yourself first, then open the answer.
Exercise 1. Operate all four rows in the tool at the top. Which cell fails, and whose side is the fault likely to be on?
Show answer
Exercise 2. A building has 10 released exit doors, 4 stair doors with re-entry, 2 held-open doors and 2 lock power supplies. Using the tool's figures, how many checks is that, and how long should you allow?
Show answer
Exercise 3. Why include a supervisory signal, such as a closed sprinkler valve, in a door release test?
Show answer
Exercise 4 (think, don't memorize). The building manager says the yearly joint test is too disruptive and asks you to sign that the doors work, based on your own test of switching off each lock power supply. What do you say?