PanelSimulator Academy

Installation, Commissioning and Maintenance, lesson 7 of 10

Commissioning tests

A system that has been switched on is not yet a system that works. Commissioning is the stage where you prove, device by device and state by state, that it does what the design promised. It is slow, repetitive and the most valuable work on the job, because every fault found now is one the customer never meets.

About 14 minutes. Read lesson 6 and "Events, alarms and monitoring" in Access Control first.

Prove one door

Run each test. The sheet on the right fills in as you go. The door is done only when every row is ticked.

reader sounder Operator's screen Door 14 test sheet

The everyday picture

Before a play opens there is a dress rehearsal. The actors know their lines and the lights are hung, but nobody calls it ready until the whole thing has been run from start to finish, with every cue. The rehearsal finds the door that sticks and the lamp pointed at the wrong chair.

Nobody rehearses only the first scene and assumes the rest is fine. And nobody rehearses only the happy scenes. The storm effect and the blackout get run too, because those are the ones most likely to go wrong on the night.

Commissioning is the dress rehearsal for a security system. Every device plays every one of its scenes while someone watches, including the scenes you hope never happen.

What commissioning means

Three ideas define a proper test.

  • It is done at the device. You stand at the door and open it. Triggering an input from the software proves the software, not the switch, the magnet, the cable or the label.
  • It is checked at the far end. The result must appear where a person will rely on it: the operator's screen, the recording, the monitoring center. This is an end-to-end test. A sensor that trips its panel while the signal never leaves the building has not passed.
  • It is written down. Each test has a line on a test sheet with the expected result, the actual result, the date and who did it. A test with no record did not happen, as far as anyone can show later.

Two people make this fast. One walks the building with a radio or phone and operates each device. The other watches the screen and fills in the sheet. One person can do it alone with a phone showing the live event list, but it takes longer and things get missed.

Commissioning ends with an acceptance test, sometimes called a witness test. The customer or their engineer watches you repeat a selection of tests, or all of them, and signs. Do your own complete run first. The witness test is a demonstration, not the moment to discover faults.

Every device, every state

A door is not one thing to test. It is a small machine with several states, and each state is a separate promise in the design. The tool at the top runs through them.

StateWhat you doWhat must happen
Valid cardPresent a card with accessLock releases, door opens, relocks when closed. Event shows the right person and the right door name.
Invalid cardPresent a card without access, then an expired oneDoor stays locked. Each refusal is recorded with its reason.
LeavingGo out from the insideThe door opens with one motion and raises no alarm
Held openEnter and hold the door openLocal warning, then an alarm at the screen after the set time
Forced openOpen the door with a key, without a cardImmediate alarm at the screen
Mains failureSwitch off the mains to the cabinetDoor keeps working on battery. A power trouble event appears.
Fire alarmHave the fire alarm contractor operate the release relayThe locks named in the design release and stay released until the alarm is reset

The same thinking applies to each input and output. A door contact has two states and you see both. A relay that drives a sounder is switched on and off. If a zone has end-of-line resistors, you also create an open and a short at the device and confirm that each reports as trouble or tamper, not as a normal alarm.

The fire alarm test is never done alone. It is arranged with the fire alarm contractor and often the building's fire authority, who may wish to witness it. "Getting out: egress and life safety" in Access Control explains what is being proved.

Check yourself

A technician triggers each door contact from the software and sees an alarm for every one. What has been proved?

Cameras, sensors and links

DeviceTests
CameraThe view matches the design. Sharp focus by day and again after dark. It is recording, and yesterday's footage plays back. The name and time on the picture are right. The stored days match what was promised.
Motion detectorA walk test: walk across the protected area at normal pace and confirm it trips where the design says, and not from outside the area. Open its cover to prove the tamper.
Door or window contactOpen and close. Confirm the right zone name. Check the gap is not at its limit by pushing the closed door both ways.
Panic or duress buttonPress it. Confirm it is silent on site if designed so, and that the right message reaches the right people.
Link to a monitoring centerEach signal type arrives and reads correctly at the center. Disconnect the main path and confirm the backup path carries it.
Links between systemsA door alarm calls up the right camera. An intercom call releases the right door.

Before sending any signal to a monitoring center, call them and place the account on test, so that operators do not dispatch the police to your walk test. Give a time for the test to end, and call again to confirm what they received. Then take the account off test. Forgetting that last call leaves a building unmonitored.

How long will it take?

Commissioning is routinely squeezed because it comes last. Estimate it honestly at the planning stage of lesson 1. The figures in the tool are placeholders. Replace them with your own timings from past jobs.

Testing time for a crew of two

Minutes are for one device, all its states, including walking to it and writing the result.

devices to prove
of testing for the crew
with a quarter added for retests

When a test fails

A failed test is the process working. Handle it the same way each time.

  1. Write down what happened, on the sheet, before touching anything.
  2. Find the cause, using the method in lesson 10. Fix the cause, not the symptom.
  3. Repeat the failed test.
  4. Repeat any test that the fix could have disturbed. If you changed a setting shared by every door, the doors already passed need a quick second look. This is called a regression test.

Resist two temptations. The first is sampling: testing a few doors and assuming the rest are the same. Each door has its own cable, its own terminations and its own lines of programming. The second is recording a pass for something that "obviously works". The sheet is a statement that you saw it happen.

Three examples

Simple: one door, seven lines

Two technicians commission a stockroom door. One stands at the door with three test cards and a key. The other reads the screen aloud over the phone. Valid card: granted, right name. No-access card: denied. Leaving: no alarm. Held: alarm at 30 seconds. Key entry: forced alarm. Mains off: still working, trouble shown. The fire alarm line is left open for the joint test on Thursday. Twelve minutes, six ticks and one line honestly blank.

Medium: right alarm, wrong door

During the walk-round, opening the east stair door raises a forced-door alarm labeled "West stair". Opening the west stair door raises one labeled "East stair". Both contacts work perfectly. Two cables were landed on each other's inputs.

A software-only test would have passed both. On a real night, a guard would have run to the wrong end of the building. Only a person standing at a named door, with another reading the name on the screen, catches this kind of fault. The fix is two wires and a retest of both doors.

Advanced: the signal that stopped at the wall

An intrusion system is commissioned carefully on site. Every zone trips, the sounder sounds and the keypad shows the right names. The monitoring link is "tested" by seeing a status light on the communicator. Three weeks later a real alarm is never received.

The account number programmed into the panel had two digits swapped. The communicator was connecting happily and the center was discarding signals it did not recognize. A true end-to-end test, with the account on test and an operator reading each signal back by zone, takes twenty minutes and would have shown an empty log at the first zone.

From the field

  • Prepare the test sheet from the drawings before you go to site, one line per device and state. Writing it on the day means lines get forgotten.
  • Carry three cards: valid, no access, expired. Add a key for every door.
  • Check cameras after dark as well. Glare, reflections from the dome and infrared bounce only show at night.
  • Read names aloud. "I am at Door 14, Stockroom. What do you see?" finds swapped cables and misspelled names at the same time.
  • Leave failed lines visible. A sheet that shows a fail, a fix and a pass is more convincing than one with only ticks.

Common mistakes

  • Testing only the valid card.
  • Testing from the software and not at the device.
  • Sampling a few devices and assuming the rest.
  • Never switching off the mains to prove the battery.
  • Skipping the fire alarm release because the other contractor was not available.
  • Sending test signals without putting the monitoring account on test, or forgetting to take it off.
  • Fixing a fault and not repeating the test.

Summary

  • Commissioning proves the system. Power-up only starts it.
  • Test at the device, check the result at the far end, and write it down.
  • Every device, in every state, including the ones you hope never to see: forced, held, power failure, fire alarm.
  • A failed test is recorded, fixed at the cause, repeated, and followed by a check of anything the fix touched.
  • Put monitoring on test before, and take it off after.

Exercises

Answer each one yourself first, then open the answer.

Exercise 1. Name four states of a controlled door that must be tested besides a valid card.

Show answer
Any four of: invalid card, leaving from inside, door held open, door forced open, mains failure, and fire alarm release.

Exercise 2. A site has 40 doors at 15 minutes each and 20 cameras at 10 minutes each. How many hours of testing is that for a crew, before any allowance for retests?

Show answer
40 times 15 is 600 minutes. 20 times 10 is 200 minutes. Together that is 800 minutes, or 13 hours and 20 minutes. With a quarter added for retests it is about 16 hours 40 minutes: two full days for two people.

Exercise 3. What must you do before and after sending test alarms to a monitoring center?

Show answer
Before: call the center and place the account on test, with an end time. After: confirm with the operator which signals arrived, then take the account off test so that real alarms are acted on again.

Exercise 4 (think, don't memorize). The project is a week late and the manager says, "Test ten doors out of sixty. They are all wired the same way." What do you say?

Show answer
They were designed the same way. They were built sixty separate times, by tired people, with sixty sets of terminations, labels and program entries. The faults commissioning finds are the ones that differ from door to door: a swapped cable, a contact at the edge of its gap, a mistyped name. A sample cannot find those. Offer a real choice instead: add a second crew to finish in the time, or hand over the tested doors now and the rest on a stated date. Then put in writing which doors have been proved and which have not, so nobody assumes more than is true.