Installation, Commissioning and Maintenance, lesson 1 of 10
Planning the job
A design on paper becomes a working system through weeks of work on a busy site, shared with other trades. Most of what goes wrong was decided before anyone picked up a drill: the wrong week, the missing part, the locked room. This lesson shows how to put the work in the right order and arrive with what you need.
Ten weeks on one job
Pick how the security work was scheduled, then play or step through the weeks.
The everyday picture
Think about redoing a kitchen. The wiring and pipes go in while the walls are bare. Then the walls are closed and painted. The cabinets, the stove and the light fittings come last. Nobody hangs a new lamp and then plasters the ceiling around it.
Do the steps out of order and you pay twice. Wiring after the paint means cutting holes in a finished wall. A stove delivered before the floor is laid sits in the hallway collecting dents.
A security installation follows the same order on a bigger site, with one extra difficulty. You are a small trade among large ones, and the building's schedule will not wait for you. Your job is to know which week is yours and to be ready for it.
Three phases of the work
Almost every installation divides into three visits to the site, with gaps in between.
- Rough-in is everything that ends up hidden. You pull cable, set back boxes in the walls, hang the cabinets and leave a labeled tail of cable at each device position. It happens while the walls and ceilings are open.
- Trim-out, also called finish, is everything people will see. You mount readers, cameras and sensors, land the wires and close the cabinets. It happens after paint, when the doors are hung and the ceiling is in.
- Commissioning is programming the system and then proving that every device works. It needs permanent power, a working network and doors that close properly. Lessons 6 and 7 cover it.
| Phase | The building must have | You leave behind |
|---|---|---|
| Rough-in | Framing up, walls and ceilings still open | Cable in place, supported and labeled at both ends. Boxes and cabinets fixed. |
| Trim-out | Paint finished, doors and hardware hung, ceiling tiles in or about to go in | Every device mounted and wired, cabinets dressed, nothing powered that has not been checked |
| Commissioning | Permanent power, network ports live, fire alarm working, doors latching | A tested system, records and trained users |
In a finished, occupied building there is no open-wall week. The work is still done in the same order, but rough-in means fishing cable through closed walls and above ceilings, which takes several times longer. Price and schedule it honestly.
At the end comes the punch list: a written list of small things still to fix, such as a missing label or a scratched cover plate. The job is finished when the list is empty, not when the last device is mounted.
Check yourself
In a new building, when is the best time to pull the cable to a door?
The other trades
On a construction site the general contractor, or GC, owns the schedule and runs a regular coordination meeting. Go to it. That meeting is where you learn that drywall has moved up a week, and where you ask for the things only other trades can give you.
| Who | What you need from them | Ask by |
|---|---|---|
| Electrician | A mains circuit at each cabinet and power supply. Conduit and boxes if the contract gives those to them. | Before rough-in |
| Door and hardware supplier | Frames and doors prepared for the electric lock, the power hinge and the door switch. The right lock on the right door. | Before doors are ordered |
| IT department | Network ports, addresses for your devices, and somewhere to put the server | Several weeks before commissioning |
| Fire alarm contractor | The relay that releases locks on alarm, and a joint test | Before commissioning |
| Elevator contractor | Cable in the elevator car and shaft. Only they work in there. | As early as possible |
The door supplier is the one people forget. A steel frame is cut for its lock at the factory. If nobody sends the supplier your door list in time, the frames arrive solid, and each one has to be cut by hand on site. Give them the list early and check it against their hardware schedule, the document that lists every part on every door.
Write requests down. An email that says "we need a dedicated 120-volt circuit at the second-floor closet by June 3" can be forwarded, tracked and pointed to later. A conversation in a corridor cannot.
Materials and lead time
Cable and screws are on a shelf at the supplier. Electrified locks, special readers and large cabinets often are not. The wait between ordering a part and receiving it is its lead time, and for door hardware it is commonly counted in weeks.
Many jobs also require a submittal first. You send the data sheets of what you intend to install to the customer's engineer, and you may not order until they approve. That approval takes time as well.
So work backwards from the week you need the part on site.
When must you order?
All figures are in weeks. Use the lead time your supplier quotes in writing.
When parts arrive, check them against the list the same day. Then stage them: sort the parts for each door into a labeled bag or box. A technician who opens the box marked "Door 14" and finds the reader, the lock, the switch, the screws and the wiring sheet does that door in half the time, and nobody raids Door 15's kit to finish it.
Access to the site
A crew that cannot get in earns nothing. Before the first day, settle these with the site contact:
- Hours and keys. When may you work, who lets you in, and which rooms are locked? Electrical and network closets usually are.
- Site rules. Many sites require a safety orientation, hard hats and proof of insurance before anyone starts. Some require background checks or an escort.
- Lifts and ladders. A camera 20 feet up a wall needs a lift, a level floor to stand it on and someone trained to use it.
- Noise and dust. In an occupied office, drilling happens before or after hours. Hospitals have strict dust rules and may ask for a sealed work tent.
- Permits. Many places require a low-voltage permit and an inspection. Ask the authority having jurisdiction before work starts, because an inspector may need to see cable before the walls close.
- Storage. Where do materials sit overnight, and who holds the key?
In a building that is in use, add one rule of your own: never leave a door less secure at the end of the day than you found it. If a lock is half changed, either finish it or put the old one back.
Three examples
Simple: three doors in a working office
A small office wants card readers on three doors. The staff work 8 to 5. The plan is two evenings. On the first, the crew pulls cable above the ceiling and hangs the cabinet. On the second, they change one lock at a time, test it, and move on only when that door locks again. The office opens each morning with every door working, either the old way or the new way.
Medium: the frames that arrived solid
On a new two-story building, the security contractor joins the job after the doors have been ordered. Twelve steel frames arrive with no opening cut for an electric strike and no path for the wire. Cutting each one on site is slow work and risks the frame's fire label, which may not allow field changes at all.
The cause was one missing email. The fix for next time is to send the door list to the hardware supplier at the start, and to compare it line by line with the hardware schedule before the order is placed.
Advanced: changing systems without a gap
A hospital is replacing an old access system with 180 doors. The building never closes. The plan divides it into areas. In each area the new cable and controllers go in beside the old ones during rough-in. On one agreed night the doors in that area are moved across, tested, and the staff's cards are checked. If something fails, the old wiring is still there to go back to.
Every area has a written plan for that night: who is on site, who to call, which doors come first, and the time at which the crew stops and rolls back. The plan is dull to write. It is the reason a ward is never left with a door that will not open.
From the field
- Walk the site with the drawings before pricing the labor. A drawing does not show the concrete ceiling, the locked riser or the 30-foot atrium.
- Read the GC's schedule every week. Find the drywall date and plan backwards from it. That date is your deadline for rough-in.
- Take a photo of every wall and ceiling before it closes, with the room number in the picture.
- Order the long-lead parts first, even if the rest of the list is not final.
- Keep a daily log. Two lines on what was done and what blocked you are worth a great deal when a delay is argued about later.
Common mistakes
- Missing the open-wall weeks, then fishing cable through finished walls at your own cost.
- Mounting readers and cameras before the painters have left.
- Assuming the electrician knows a circuit is needed at your cabinet.
- Ordering locks the week they are needed.
- Starting to commission before permanent power and the network exist.
- Leaving a door in an occupied building half converted overnight.
Summary
- The work has three phases: rough-in while walls are open, trim-out after paint, commissioning once power and network are permanent.
- The general contractor's schedule sets your dates. The drywall date matters most.
- Ask other trades in writing, early, for power, door preparation, network and the fire alarm relay.
- Count backwards from the week you need a part: margin, lead time, then approval.
- Settle hours, keys, lifts, permits and storage before the first day.
Exercises
Answer each one yourself first, then open the answer.
Exercise 1. Put these in order: mount the reader, pull the cable, test the door, paint the wall.
Show answer
Exercise 2. Trim-out starts in 9 weeks. The locks have a 6-week lead time and the submittal takes 2 weeks to approve. You want 1 week of margin. When must the submittal go in?
Show answer
Exercise 3. Name three things you need from other trades before you can commission a door.
Show answer
Exercise 4 (think, don't memorize). The GC tells you on Monday that drywall starts Thursday, a week early. You have pulled cable to half the doors. What do you do?