Doors and Locking Hardware, lesson 10 of 10
Reading a hardware schedule
On a building project, nobody describes doors in sentences. Every opening is a row in one table and a list of parts in another. This last lesson teaches you to read both, using every term from the course, and to spot the gaps between the hardware supplier's work and yours before they become a problem on site.
Read a hardware set
Pick an opening. The row is from the door schedule. The list is its hardware set. Click any line to find the part on the door.
The everyday picture
A restaurant kitchen does not write a new recipe for every plate. It has a menu with numbered dishes, and each order ticket says "table 12: two of number 4, one of number 9". The recipe for number 4 is written once.
Building documents treat doors the same way. One table lists every opening and gives each a set number. A second document writes out each numbered set once: the "recipe" of hinges, lock, closer and the rest. A building with 300 doors may need only 25 different sets.
Two documents that work together
The door schedule is a table on the architectural drawings, with one row for each opening. It describes the door and frame and points to a hardware set. The hardware schedule lists what is in each set. Early in a project the sets appear in the written specification, in the section for door hardware. Later, the hardware supplier turns them into a detailed schedule with exact catalog numbers, and submits it for approval before ordering.
| Door schedule column | What it tells you | Lesson |
|---|---|---|
| Number | The opening's name, usually the room number, with a letter if the room has several doors | |
| Size | Width and height, as 3070, and the thickness | 1 |
| Door and frame | Type and material: HM for hollow metal, WD for wood, AL for aluminum | 1 |
| Rating | The fire rating in minutes, or blank for none | 8 |
| Hand | LH, RH, LHR or RHR. Sometimes shown only on the plan, by the swing. | |
| Hardware set | The number of the set that applies | |
| Remarks | Anything unusual: card reader, undercut, sound seals |
Always read the row and the set together, and then find the door on the floor plan. The plan shows the swing, which wall the reader could go on, and what is behind that wall.
Reading a line
Each line in a set has the same shape: a quantity, a unit, the item, a description, a finish and often a maker. Sets are written in a customary order that follows the life of the door: what hangs it, what secures it, what closes it, what protects it, and last what seals it.
- Quantity and unit. EA means each. Hinges are sometimes counted in pairs, so three hinges may be written as 1 1/2 PR. A SET usually means seals for one whole frame.
- Item and description. The lesson 2 terms appear here for hinges, the lesson 3 function for locks, the lesson 5 mounting for closers.
- Quantities are for one opening. A set used on 14 doors lists 3 hinges, not 42. The heading of the set says which openings use it.
- Options ride on the catalog number. Suffixes add features such as a non-removable pin, a request to exit switch or a fire label. A missing suffix is a missing feature.
Check yourself
A hardware set heading lists 12 openings. One line reads "3 EA hinges". How many hinges does the supplier order for that set?
Abbreviations and finishes
Schedules are terse. These are the short forms you will meet most. Projects add their own, so look for the legend at the front.
| Short form | Meaning |
|---|---|
| EA, PR, SET | Each, pair, set |
| HM, WD, AL | Hollow metal, wood, aluminum |
| LH, RH, LHR, RHR | The four hands of a door |
| NRP | Non-removable pin |
| KD, KA, MK, GMK | Keyed different, keyed alike, master keyed, grand master keyed |
| IC | Interchangeable core |
| DPS, REX | Door position switch, request to exit |
| EPT | Electric power transfer, which carries wire from frame to door |
| FS, FSE | Fail-safe and fail-secure |
| By others | Supplied under a different contract. Find out whose. |
Finishes are given as three-digit codes from the builders hardware industry standard. You do not need them all. Satin chrome is 626, the most common commercial finish. Satin stainless steel is 630. Hinges in satin chrome on steel are 652. Closers painted aluminum color are 689. Dark oil-rubbed bronze is 613. Older documents use codes beginning with US, such as US26D for satin chrome.
Electrified openings
This is where a security integrator must read most carefully, because the opening is split between trades. The hardware supplier usually provides everything that mounts on the door and frame. The security contractor usually provides the reader, the controller, the cable and often the power supply. The electrician provides mains power and often conduit. Every item must be someone's.
For each electrified opening, a good schedule includes three extra things.
- A complete parts chain. An electrified lock in the door needs a power transfer to feed it and a raceway through the door. An electric strike needs a frame prepared for it. Check that each part's partner is listed.
- Electrical data. Voltage, current and whether each lock is fail-safe or fail-secure. You need these to size the power supply, as the Access Control lesson "Power supplies and batteries" showed.
- An operational description. A short paragraph saying what the door does: how it is entered, how people leave, what happens on fire alarm and on power loss. If you cannot write this paragraph from the parts listed, something is missing.
The supplier also provides wiring diagrams for electrified sets: one showing how the devices connect in general, and one showing each wire terminal by terminal. Ask for them with the approved schedule, not on the day of installation.
Count the parts
Estimators turn a schedule into totals. Try it for a small project. A single door 7 feet high has three hinges and one with 8 feet has four. A pair has two leaves, so double everything that goes on a leaf.
A quick takeoff
Three examples
Simple: the hand that was never checked
Twelve exit devices arrive for the corridor doors of a school wing. Eight fit. Four are handed the wrong way, because the schedule gave no hand and the supplier guessed from a typical door. A look at the plan, where each swing is drawn, would have taken ten minutes. Since then, your survey sheet has a hand column, and you compare it with the schedule before approving anything.
Medium: the lock with no power
You are reviewing a submitted schedule for a clinic. Set 9, for the pharmacy door, lists an electrified mortise lock, fail-secure, 24 volts. It lists standard hinges and nothing else electrical. There is no power transfer, the door schedule shows no raceway, and the power supply is "by others" with nobody named.
You send three written questions before approval: add an electric power transfer and raceway prep, confirm who supplies the power supply, and state the lock's current. Caught on paper, this costs nothing. Caught after the doors are hung, it means removing a labeled door and sending it to a shop.
Advanced: writing the operational description
A stair door set lists fire exit hardware with electrified lever trim, a power transfer, a closer, a door position switch and "card reader by security contractor". The architect asks you to draft the description.
You write: "The door is normally closed and latched. The stair-side lever is locked. A valid card at the stair-side reader unlocks the lever for a set time. Leaving the floor is always free by the push bar, which signals a request to exit. On fire alarm or loss of power the stair-side lever unlocks, and the door remains latched. The door position switch reports a door forced or held open." Writing it exposes one open question, which is whether re-entry on fire alarm is required here. That goes to the authority having jurisdiction, and the answer fixes the trim as fail-safe.
From the field
- Mark up a floor plan. Highlight every electrified opening and write its set number beside it. Patterns and omissions show at once.
- Check the rating column against every electrified set. A rated door needs listed electrified hardware and factory preps.
- Ask for the approved schedule, not the specification. The spec says what was intended. The approved submittal says what is being delivered.
- Read the remarks column. "Card reader", "future card reader" and "rough-in only" mean very different amounts of work.
- Keep the schedule after handover. It is the parts list for every future repair.
Common mistakes
- Reading the hardware set without the door schedule row, and missing the fire rating or the size.
- Treating "by others" as somebody else's problem instead of finding out who.
- Pricing a card access job from the plan alone, without seeing which locks the hardware supplier is providing.
- Assuming the same set number means the same hand on every door.
- Accepting an electrified set with no operational description and no wiring diagram.
Summary
- The door schedule has one row for each opening and points to a hardware set.
- A hardware set lists the parts for one opening: hang it, secure it, close it, protect it, seal it.
- Each line gives quantity, item, description and finish. Options hide in the catalog number.
- For electrified openings, check the parts chain, the electrical data and the operational description.
- Every "by others" needs a name before the job starts.
Exercises
Answer each one yourself first, then open the answer.
Exercise 1. A door schedule row reads: 204A, 3070 x 1 3/4, HM door, HM frame, 45 min, RHR, set 6. Describe the opening in a sentence.
Show answer
Exercise 2. A set used on 9 single doors lists 1 1/2 PR hinges, 1 EA closer and 3 EA silencers. Give the totals to order.
Show answer
Exercise 3. What finish do the codes 626 and 630 describe?
Show answer
Exercise 4 (think, don't memorize). You receive a set for a pair of fire-rated doors: 6 hinges, automatic flush bolts, a storeroom lock, an electric strike, two closers and an overlapping astragal. Using what you learned in this course, list what you would question.