PanelSimulator Academy

Codes, Standards and Privacy, lesson 7 of 10

Licenses and permits

A license says a company or a person is allowed to do a kind of work. A permit says one particular job has been looked at and may go ahead. This lesson explains both, why they differ so much from state to state, and the order of paperwork on a well-run job.

About 14 minutes. Read lesson 2 of this course first.

A job, from license to sign-off

Pick a situation, then play or step through it.

before the job after the job 1 2 3 4 5 6 License Application Plan review Work Inspection Closeout company, people drawings, fee permit issued permit on site rough, then final owner records permit Stop work fire alarm firm

The everyday picture

A driver's license says you are allowed to drive. It took a test, and it is yours for years. A parking permit says this car may be in this street on this day. You need both, and neither replaces the other.

Construction works the same way. A license belongs to a company or a person and says they are qualified and accountable. A permit belongs to one job at one address and says the local authority has seen the plan. A licensed company still needs a permit for each job that requires one. And a permit cannot be issued to a company that has no license to do that work.

Licenses: who may do the work

There is no national license for security installation in the United States. Each state decides, and the differences are large. Some states license alarm and access control companies through a dedicated board. Some fold the work into a low-voltage or limited-energy electrical license. Some license locksmiths separately. A few leave most of it to cities and counties. The only reliable source is the licensing agency of the state, and often the city, where the job is.

Whatever the state calls them, the requirements tend to come in layers.

LayerWhat it usually involvesWhy it exists
Company licenseA named qualifying person who passed an exam, proof of insurance, sometimes a bondSomeone accountable if the work is bad
Individual registrationA background check, often fingerprints, sometimes training hours. It can cover salespeople as well as technicians.These people learn where a customer's valuables are and how the alarm is set
Specialty licenseSeparate licenses for fire alarm, locksmithing or electrical workEach trade has its own hazards
RenewalFees and continuing education every year or twoCodes change

A certification is a different thing. It is a credential from a trade body or a manufacturer that shows you passed a course or an exam. Some are highly respected, and a specification or an AHJ may demand one, as fire alarm work often demands certified technicians. A certification is not permission from the state. You may need both.

Working without a required license is serious. Depending on the state it can mean fines, an order to stop, and criminal charges. In many states an unlicensed contractor also cannot go to court to collect what a customer owes. Licenses rarely carry across state lines, so a company that wins work in a new state checks that state's rules before it sends a truck.

Check yourself

A technician holds a manufacturer's certification for an access control system. The state requires a license for that work. Is the certificate enough?

Where your license stops

A security license covers security work. On most jobs you will meet the edge of it several times. Knowing where the edge is, and who to call, is part of the trade.

  • The 120-volt feed to a power supply is electrical work, done by a licensed electrician in most states.
  • The connection at the fire alarm panel belongs to a licensed fire alarm contractor, usually the firm that maintains that building's system. You provide the relay and the cable on your side.
  • Wiring in an elevator car or shaft is done by the elevator contractor. You hand over an interface at the machine room.
  • Preparing a fire door beyond the limits of NFPA 80 belongs to a shop working under a label program, as lesson 3 explained.
  • Cylinders and keying may need a locksmith license where the state has one.

Permits: permission for one job

Whether a job needs a permit depends on the city or county, and on what the job touches. Like-for-like repair often needs none. New wiring, and anything that changes how an exit door locks, often does.

PermitTypically coversIssued by
Low-voltage or electricalNew cable and devicesBuilding or electrical department
BuildingChanges to doors, frames, walls or exitsBuilding department
Fire alarmAny change to the fire alarm system, including a new relay for door releaseFire prevention office
Access control or special lockingMagnetic locks, delayed egress and similar arrangements on exit doors. Some cities have a dedicated permit.Fire or building department
Alarm user permitThe right to have a monitored burglar alarm that calls the police. It belongs to the owner, not the installer.Police department or city

A permit application is a small package: a form with the contractor's license number, floor plans showing devices, a wiring diagram, a description of how each door behaves on an ordinary day, in a fire alarm and in a power cut, product data sheets, and a fee. Some jurisdictions want drawings sealed by a licensed engineer. Review can take a day or several weeks, so the application goes in early. Work starts when the permit is issued, and the permit is kept at the site.

Two approvals sit outside the government. Tenants need the landlord's written consent to alter a building. And before anyone digs a trench, the utility locating service must mark buried lines. Dialing 811 reaches it anywhere in the country.

Inspection and closeout

Most permits bring two inspections. The rough-in inspection happens while cable and boxes can still be seen, before ceilings and walls are closed. The final inspection happens when everything works. For doors tied to the fire alarm, the fire marshal will usually want to see the alarm triggered and every lock release.

A job is closed when the inspector signs it off. The owner should then receive a set of records: the signed permit, drawings showing what was actually built, test results, any written approvals from the AHJ, and manuals. Fire alarm work has its own formal record of completion. On a new building, these sign-offs feed into the certificate of occupancy, which is what lets the owner open the doors.

What will this job need?

Pick a job to see the paperwork it commonly brings. These are typical patterns and not the law in your town. The last line of each tells you who to ask.

Choose a job

Paperwork to expect
Other trades to bring in
Ask first

Three examples

Simple: the weekend favor

A technician agrees to fit a small alarm at a friend's shop on a Saturday, for cash. His employer holds the state alarm license. He does not hold one himself, and the job is not on the company's books.

In a state that licenses alarm work, he has just contracted without a license. If the alarm fails during a burglary, there is no insurance behind the work. The honest route costs the friend little more: the job goes through the licensed company, with a permit if the city wants one.

Medium: the ceiling that had to come down

A contractor wires twelve doors in a new office fit-out and the ceiling crew closes up behind him. No low-voltage permit was pulled, because "it is only access control". At the building final, the inspector asks for it.

The city issues a permit after the fact at a multiple of the normal fee and requires a rough-in inspection. Tiles are lifted along every cable route so that supports and firestopping can be seen. Two firestop seals are missing. The tenant's move-in slips by a week. The permit would have cost an hour of paperwork.

Advanced: a new state, a hospital, a deadline

An integrator wins a hospital project in a neighboring state. Before mobilizing, the project manager makes a list. The company needs that state's contractor license, which requires a qualifying employee to sit an exam. Each technician needs to be registered there, with fingerprints. The door release relays need a fire alarm permit, and the hospital's fire alarm firm must make the panel connection. The locked unit needs the approvals described in lesson 2.

The licensing alone takes two months. She tells the customer on day one, puts the dates in the schedule, and starts the applications before the contract is signed. The job finishes on time because the paperwork was treated as work.

From the field

  • Carry your registration card. Inspectors and some customers ask to see it.
  • Call the permit counter and ask, "Does this scope need a permit, and which one?" Write down the name and the date.
  • Book the rough-in inspection before the ceiling crew arrives, not after.
  • Put the license number on proposals and vehicles where the state requires it. Many do.
  • Hand the owner a closeout folder. The next inspector, and the next contractor, will ask for it.

Common mistakes

  • Assuming a license from one state is good in the next.
  • Believing low-voltage work never needs a permit.
  • Treating a manufacturer's certificate as a license.
  • Making the fire alarm panel connection yourself to save a visit.
  • Leaving the permit and approvals in the office, with nothing at the site.

Summary

  • A license qualifies a company or person. A permit approves one job. You may need both.
  • Licensing is set by each state, and sometimes each city. Check the agency where the job is.
  • Certifications show skill and are sometimes required, and they do not replace a license.
  • Power, fire alarm, elevator and fire door work each belong to their own licensed trade.
  • Apply early, keep the permit on site, get inspected before things are covered, and give the owner the records.

Exercises

Answer each one yourself first, then open the answer.

Exercise 1. In one sentence each, what does a license attach to, and what does a permit attach to?

Show answer
A license attaches to a company or a person. A permit attaches to one job at one address.

Exercise 2. Why do many states require a background check for alarm salespeople, who never touch a wire?

Show answer
A salesperson walks through the building, learns what is worth stealing, where the sensors will be and how the customer uses the system. The check is about trust in the person, not skill with tools.

Exercise 3. What is the rough-in inspection for, and what happens if you miss it?

Show answer
It lets the inspector see cable types, supports and firestopping before they are hidden. If it is missed, the inspector can require ceilings or walls to be opened. Step through "Work started with no permit" at the top.

Exercise 4 (think, don't memorize). A customer says, "Skip the permit. It adds two weeks, and nobody will ever know." Give three reasons to refuse that are in the customer's own interest.

Show answer
First, unpermitted work tends to surface at the worst time: a later inspection, a sale of the building, or an insurance claim after a fire, when an insurer may question work that was never inspected. Second, plan review is a free check of the design by the person who will judge it, and it is far cheaper to change a drawing than a finished door. Third, if the work is found, the owner pays penalty fees and the cost of opening things up, and loses more than two weeks. You can also offer to shorten the wait by applying today.