Codes, Standards and Privacy, lesson 4 of 10
The electrical code
Security wiring is low voltage, and low voltage is still wiring. This lesson explains what the National Electrical Code asks of the cable you pull, in plain words: which circuits count as power-limited, which cable goes in which space, and the handful of installation rules inspectors check first.
Match the cable to the space it runs through
Choose where the cable runs and what is printed on its jacket. The building is cut through from the side.
The everyday picture
A garden hose and a fire hose both carry water. You can leave a garden hose lying on the lawn, and if it splits you get wet shoes. A fire hose can knock you over, so it is stored, connected and handled by rules.
The electrical code sorts circuits the same way. A circuit that cannot deliver enough energy to start a fire or give a dangerous shock is treated lightly. It may use thin cable, without conduit, run by people who are not electricians. A circuit that can do harm is treated as power wiring. Most security wiring sits in the first group, and the code's low-voltage rules are mainly about making sure it stays there.
What NFPA 70 is
NFPA 70 is the National Electrical Code, usually shortened to NEC. It is the model code for electrical installation in the United States, reissued every three years and adopted state by state, as lesson 2 described. Its purpose is narrow: to protect people and property from the hazards of electricity. It does not care whether your system works well.
The book is divided into numbered articles. The ones a security installer meets most are these.
- The general articles on wiring methods, boxes and grounding, which govern the 120-volt feed to your power supplies.
- Article 725, long the home of the power-limited circuits that run readers, locks, sensors and keypads. Recent editions have moved parts of it into neighboring articles, so use the index of the edition your state adopted.
- Article 760, fire alarm circuits.
- Article 800 and its neighbors, communications circuits, which is where network cable belongs.
Three classes of circuit
The code sorts control and signal circuits into three classes, by how much the power source can deliver.
| Class | What the source can do | How it is wired |
|---|---|---|
| Class 2 | Limited so that a fault should neither start a fire nor give a dangerous shock. At the 12 and 24 volts we use, that means roughly 100 volt-amperes per circuit. | Light cable, no conduit required by this code, kept apart from power wiring |
| Class 3 | Limited against fire, at higher voltage, so a shock is possible | Similar freedom, with tougher cable |
| Class 1 | Not power-limited in the same way | With the methods used for ordinary power wiring |
What makes a circuit Class 2 is its source, not its cable or its voltage. The power supply or transformer must be listed and marked "Class 2". Look for those words on the label. A large lock power supply may have some outputs that are Class 2 and a main output that is not. Wire from the wrong terminal and your thin lock cable has become a Class 1 circuit that needs power wiring methods.
Power over Ethernet is a Class 2 source as well. Recent editions add rules for big bundles of cable carrying the higher PoE power levels, because cables packed together warm each other up.
Check yourself
What makes a lock circuit a Class 2 circuit?
Reading a cable jacket
Every listed cable has its type printed along the jacket. The letters tell you which circuits it is for and which spaces it may run through. The tool at the top of this page shows the three kinds of space.
| Space | Why it matters | Power-limited | Communications | Fire alarm |
|---|---|---|---|---|
| Plenum: a space that moves air for the building, most often above a suspended ceiling | Smoke from a burning jacket would be carried to every room | CL2P, CL3P | CMP | FPLP |
| Riser: a vertical run from floor to floor | A shaft can carry flame upward like a chimney | CL2R, CL3R | CMR | FPLR |
| General: anywhere else inside | Ordinary fire resistance is enough | CL2, CL3 | CM | FPL |
A better cable may always stand in for a lesser one. Plenum cable can go anywhere. Riser cable can go in a riser or a general space. General cable can go only in a general space. Not every ceiling space is a plenum, and the mechanical drawings or the building engineer will tell you. If you cannot find out, treat it as one.
Two more markings come up often. Cable that runs outdoors or underground must be rated for wet locations, and the inside of a buried conduit counts as wet. Devices mounted in a plenum, such as a sensor above the ceiling, need their own plenum rating too.
Rules for the installer
- Keep power-limited cable apart from power wiring. It may not share a conduit, a box or a compartment with 120-volt conductors unless a barrier separates them. Inside a cabinet, follow the routing shown on the installation sheet.
- Support cable from the building structure. It may not lie on the ceiling tiles or be tied to the ceiling grid, to sprinkler pipe, to ductwork or to another trade's conduit. Use hooks or rings fixed to the structure, or dedicated support wires.
- Seal every hole in a rated wall or floor. A hole for one cable through a fire-rated wall has to be closed with a listed firestop system, installed as its instructions say.
- Remove abandoned cable. Old cable that is not in use and not tagged for future use is fuel. The code expects the accessible parts to come out.
- Use listed equipment as its instructions say. The instructions are part of the listing. Lesson 6 explains why.
- Work neatly. The code asks for a neat and workmanlike installation. Inspectors treat tidy work as a sign that the hidden parts are right too.
The 120-volt connection to a power supply is power wiring. In most states it must be made by a licensed electrician, on a circuit installed under an electrical permit. Lesson 7 covers who may do what.
Would this pass?
Eight things an inspector might find
Decide whether each one is acceptable, then read why.
Three examples
Simple: the box of cable in the van
A technician has to run a reader cable 60 feet above a suspended ceiling in an office. The van holds a box marked CL2 and a box marked CL2P. He lifts a tile and sees no ducts connected to the return grilles: the air simply flows back through the open ceiling space. That makes it a plenum. He takes the CL2P box.
Medium: the supply with two kinds of output
A lock power supply rated at 10 amps and 24 volts feeds eight doors. Its label says the eight fused outputs are Class 2 power-limited, and the main terminals are not. An installer, short of outputs, lands a ninth lock straight on the main terminals with ordinary lock cable.
The sum explains the problem. 10 amps at 24 volts is 240 volt-amperes, well beyond what a Class 2 circuit may deliver. A short on that cable could draw far more current than the thin wire can carry safely. The fix is a second listed supply or an output module, so that every lock cable starts at a Class 2 terminal.
Advanced: the retrofit above the corridor
A school replaces its old intercom and access wiring. Above the corridor ceiling the crew finds three generations of dead cable lying on the tiles, and a fire-rated wall with a fist-sized hole stuffed with rags. The corridor ceiling is a return-air plenum.
The plan that passes inspection has four parts. The dead cable comes out. New plenum cable hangs from hooks fixed to the structure, clear of the tiles. The hole is closed with a listed firestop system sized for the bundle, with a label beside it. And the contract says in advance who pays for removal and firestopping, because both take longer than pulling the new cable.
From the field
- Read the jacket before you pull, not after. Boxes get refilled with the wrong reel.
- Carry firestop that is listed for your cable and wall type, and keep the instruction sheet. Red caulk from any tube is not a firestop system.
- Take a photo above the ceiling when you finish. It is your proof of supports and firestopping after the tiles go back.
- Leave the 120-volt work to the electrician and coordinate where the outlet or junction box goes.
- Ask the inspector which edition and which amendments apply before a large job. Some cities require conduit or plenum cable everywhere.
Common mistakes
- Assuming low voltage means no code applies.
- Running general-purpose cable above a ceiling without checking whether it carries air.
- Laying cable on ceiling tiles or tying it to sprinkler pipe.
- Sharing a conduit or box with 120-volt wiring.
- Feeding thin cable from a supply terminal that is not marked Class 2.
Summary
- NFPA 70, the National Electrical Code, covers low-voltage wiring as well as power wiring.
- A circuit is Class 2 because its source is listed and marked Class 2.
- The letters on the jacket say where a cable may run: plenum, riser or general. A better cable may replace a lesser one.
- Keep it apart from power wiring, support it from the structure, firestop the holes and remove the dead cable.
- Article numbers and details shift between editions, and cities amend them. Check what was adopted.
Exercises
Answer each one yourself first, then open the answer.
Exercise 1. You have a reel marked CMR. In which of the three kinds of space may it run?
Show answer
Exercise 2. A supply output is fused at 2.5 amps and delivers 24 volts. How many volt-amperes is that, and is it within the rough Class 2 figure in this lesson?
Show answer
Exercise 3. Why may a cable not rest on the ceiling tiles, even if it is plenum rated?
Show answer
Exercise 4 (think, don't memorize). A customer wants a camera on a pole in the parking lot, fed by network cable through a buried plastic conduit from the building. Ordinary indoor CMR cable is on the truck. What do you think about before using it?